File #: 24-5715    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/5/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of a change in contract with Sweeping Corporation of America, Inc., in connection with final On-Call - Maintenance - Street Sweeping, Wade Camp - Precinct 2 - 2022, with a deduction in the amount of $29,474.01, Job No. 22/0451-1, UPIN 23102MF2WT01, Precinct 2, Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable):  Job No. 22/0451, UPIN 23102MF2WT01

Vendor/Entity Legal Name: Sweeping Corporation of America, Inc.

 

MWDBE Contracted Goal (if applicable): 0%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  0% - Non-Divisible

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Sweeping Corporation of America, Inc., in connection with final On-Call - Maintenance - Street Sweeping, Wade Camp - Precinct 2 - 2022, with a deduction in the amount of $29,474.01, Job No. 22/0451-1, UPIN 23102MF2WT01, Precinct 2, Justification for 0% MWDBE Participation Goal:  0% - Non-Divisible.

end

 

Background and Discussion:

This project is a maintenance contract for the street sweeping in the Wade Camp Area - Precinct 2.  The contract is being closed at the request of the Precinct, and in accordance with the recommendation of Harris County Engineering Department.

 

Expected Impact:

The change allows unused funds to be returned to the Precinct.

 

Alternative Options:

Maintain the original scope of the project.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation                     

_ Flooding

X Environment

_ Governance and Customer Service

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

02/21/2023

23-1107

Contract Award

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

-$29,474.01

-$29,474.01

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

-$29,474.01

-$29,474.01

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

-$29,474.01

-$29,474.01

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: September 19, 2024

Anticipated Implementation Date (if different from Court date): n/a

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Projects Infrastructure, Harris County Engineering Department