File #: 25-2726    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action: 5/8/2025
Title: Request for approval to execute a Service Outlet Location Statement for Installation of electric Poles to avoid conflict with the proposed Harris County traffic signal Master pole at the Intersection of Imperial Valley Drive and Doubletree Glen Drive, UPIN 23101MF2XP01, Precinct 1.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

 

Project ID (if applicable): 23101MF2XP01

Vendor/Entity Legal Name (if applicable): CenterPoint Energy

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute a Service Outlet Location Statement for Installation of electric Poles to avoid conflict with the proposed Harris County traffic signal Master pole at the Intersection of Imperial Valley Drive and Doubletree Glen Drive, UPIN 23101MF2XP01, Precinct 1.

end

 

Background and Discussion:

Installing a new traffic signal at the intersection of Imperial Valley Drive and Doubletree Glen Drive is a project aimed at enhancing traffic flow at the existing intersection. The service outlet location statement is needed to Remove 55ft CenterPoint Electric Power Pole and Installation of 65ft Pole to avoid conflict from HC Proposed Master Pole for traffic signal lights.

Expected Impact:

Approval of the service outlet location statement will allow CenterPoint Energy, to Install 65 Ft Electric polls, which is needed to avoid Conflict and enhance the operation of the intersection of Imperial Valley Drive and Doubletree Glen Drive.

Alternative Options:

No alternative options, the Poles must be raised to avoid conflict.


County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location: Intersection of Imperial Valley Drive and Doubletree Glen Drive
Address (if applicable): N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services

Office of the County Engineer

 

Attachments (if applicable): N/A