Title: Request for approval of a certain project, decreeing the project to be a public necessity and convenience, directing the Harris County Real Property Division to acquire, one (1) fee simple and thirteen (13) temporary construction easement tracts for the public project known as Cypress North Houston Rd - from Perry Rd to Jones Rd - 2014, for the purpose of roadway construction, UPIN 15104MF0CD01, Precinct 3.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: Not applicable

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

 

Project ID (if applicable): 15104MF0CD01

Vendor/Entity Legal Name (if applicable): Any applicable landowner and/or property interest holder

 

MWBE Contracted Goal (if applicable): Not applicable

MWBE Current Participation (if applicable): Not applicable

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): Not applicable

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a certain project, decreeing the project to be a public necessity and convenience, directing the Harris County Real Property Division to acquire, one (1) fee simple and thirteen (13) temporary construction easement tracts for the public project known as Cypress North Houston Rd - from Perry Rd to Jones Rd - 2014, for the purpose of roadway construction, UPIN 15104MF0CD01, Precinct 3.

end

 

Background and Discussion:

The project involves the design and construction of the proposed expansion of Cypress North Houston from Jones Rd to Perry Rd to result in a four-lane concrete boulevard. The project includes storm drain and sidewalks and detention basin mitigation and traffic signals at Perry Road, Autumn Mill Drive, and Misty Moss Lane.

 

 

Expected Impact:

The project will address current and future traffic volumes, reduce delays, and provide safe mobility for residents, pedestrians, and drivers.

 

 

Alternative Options:

If no action is taken, there will be delays in area mobility improvement.

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any): None

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Various Locations (see attachments)

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 11/13/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Dr. F. Mike Etienne, Chief of Planning and Development Services, Office of the County Engineer

 

Attachments (if applicable): Findings and Declarations; Metes and Bounds