Legislation Details

File #: 24-6617    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 10/15/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Southwest Signal Supply, Inc., in connection with Intersection Improvement - Telge at US 290 - 2022, Job No. 23/0341, UPIN 23103MF2R101, Precinct 3.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

 

Project ID (if applicable): Job No. 23/0341, UPIN 23103MF2R101

Vendor/Entity Legal Name (if applicable): Southwest Signal Supply, Inc.

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Participation (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Transmittal by the Office of the County Engineer of a substantial completion certificate with Southwest Signal Supply, Inc., in connection with Intersection Improvement - Telge at US 290 - 2022, Job No. 23/0341, UPIN 23103MF2R101, Precinct 3.

end

 

Background and Discussion:

The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset.  The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001.  These certificates provide a method by which Harris County may document and record this date.

 

Expected Impact:

This action establishes the date on which a capital improvement enters service as a Harris County asset.

 

Alternative Options:

 

No alternative option

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X_ Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/30/2024

24-0571

Contract Award

 

Location:

Address (if applicable): Telge at US 290

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: October 29, 2024

Anticipated Implementation Date (if different from Court date): n/a

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Erwin Burden, PE, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

Attachments (if applicable): Substantial Completion Form