File #: 26-6660    Version: 1 Name:
Type: Contract - Award Status: Agenda Ready
File created: 10/1/2026 In control: Commissioners Court
On agenda: 10/15/2026 Final action:
Title: Request for approval to execute an agreement with IEA, Inc., in the amount of $556,766.00, for professional engineering services in connection with Wastewater Connection to Pearland - Tom Bass 1 - 2026, UPIN 26101LT7HH01, Precinct 1, MWBE Contracted Goal: 18.00%.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Secondary Department: Commissioner, Precinct 1

Secondary Department Head/Elected Official: Adrian Garcia, Commissioner

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 26101LT7HH01

Vendor/Entity Legal Name (if applicable): IEA, Inc.

 

MWBE Contracted Goal (if applicable): 18.00%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with IEA, Inc., in the amount of $556,766.00, for professional engineering services in connection with Wastewater Connection to Pearland - Tom Bass 1 - 2026, UPIN 26101LT7HH01, Precinct 1, MWBE Contracted Goal: 18.00%.

end

 

Background and Discussion:

Harris County Precinct 1 has requested that the Office of the County Engineer initiate a wastewater project at Tom Bass Park Section 1, to address sanitary sewer system capacity limitations associated with the existing lift station network. Tom Bass 3 Main Lift Station has experienced sanitary sewer overflows. Capacity Assessments were performed and it was determined that the lift station is undersized and the overflows were due to flows from multiple park lift stations. The purpose of this project is to reduce the flows to the Tom Bass 3 Main Lift Station and divert wastewater flow from Tom Bass Park Section 1 to the City of Pearland collection system, which has been determined to have available capacity to receive the additional flows.

 

Expected Impact:

IEA, Inc. will design and prepare construction documents needed to alleviate the sanitary sewer overflows at Tom Bass 3 Main Lift Station.

 

 

 

Alternative Options:

If no action is taken, Tom Bass 3 Main Lift Station will continue to experience sanitary sewer overflows and may incur TCEQ violations for Unauthorized Discharges.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H4: Consistently embed sustainability considerations in the project planning and design process.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): Tom Bass Park Section 1

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Professional Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Bonds 2022

$

$556,766.00

$556,766.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$556,766.00

$556,766.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$556,766.00

$556,766.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 10/15/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer

 