Legislation Details

File #: 26-4151    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/23/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $351,403.24, Job No. 24/0139-7, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0139, UPIN 21289MF1Z501

Vendor/Entity Legal Name (if applicable): Precise Services, Inc.

 

MWBE Contracted Goal (if applicable): 25.22%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $351,403.24, Job No. 24/0139-7, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.

end

 

Background and Discussion:

In response to the destruction wrought by Hurricane Harvey that underscored critical shortages in Harris County’s inventory of affordable homes, Harris County’s Single-Family New Construction Program (SFNCP) matches individuals and families with opportunities to purchase new affordable homes in growing developments throughout the county.  Task Order 6: includes construction of roadways and sidewalks, Installation of sanitary sewer and storm systems, Pavement improvements, Construction of a lift station and detention ponds.

This change order is tied to PCO -14 & PCO-15: PCO-14: Overrun Quantity Bid Items: Multiple bid items at the Connorvale Development project experienced quantity overruns due to unforeseen site conditions, design modifications, safety requirements, regulatory compliance, and approved RFIs and change directives from Harris County, HCD and the Engineer of Record (EOR).  In addition, the consulting engineer’s initial bid quantity estimates were underestimated for certain items, which contributed to the resulting overruns.  The additional work was required to complete construction as designed, maintain safety, and ensure proper drainage and environmental compliance. All extra quantities were paid at original contract unit prices.

The overruns include various infrastructure and utility items such as demolition work, waterline and storm sewer installation, trench safety systems, pavement and curb work, erosion control measures, borrow material, traffic control, SWPPP inspections, and drainage structures including manholes, inlets, junction boxes, and reinforced concrete pipes.  Some items were also impacted by approved time extensions and field adjustments. The resulting quantity overrun change order totals $207,403.24 (approximately 5.06% of the project budget), with no additional days to the project contract time.

PCO-15: Detention Pond Slope Restoration and Vegetation Enhancement: The detention pond back slopes have experienced erosion due to inadequate vegetation establishment, resulting in continued slope instability and the need for corrective stabilization measures to ensure long-term performance and compliance with project requirements.  The EOR and OCE project team determined that these deficiencies were primarily attributable to the Contractor’s failure to properly establish vegetation, rather than the sandy soil conditions cited by the Contractor.

As the erosion issues remained unresolved since August 2025, the matter was escalated to OCE Leadership and extensively coordinated among project stakeholders.  Following negotiations, the Contractor submitted a revised proposal that includes Regrading the pond slopes, restoring disturbed areas, and installing full in-place sod for erosion control.  The proposed corrective scope and associated cost of $144,000.00 were reviewed and approved by OCE Leadership and HCD.  Accordingly, this approval results in a proposed Change Order in the amount of $144,000.00 to be added to the project cost.

Summary of PCO-14 & PCO-15: PCO-14 addresses quantity overruns for existing bid items only, with no new line items added, totaling $207,403.24. PCO-15 covers new line-item number Detention Pond Slope Restoration and Vegetation Enhancement in the amount of $144,000.00.  Together, these proposed change orders increase the total project cost by $351,403.24, representing approximately 8.55% of the overall project budget, with no additional days to the contract time.

Expected Impact: The changes enable adding new item quantities to the contract, ensuring the project aligns with its originally intended objectives.  This change order adds $351,403.24 to the project contract amount, with no additional days.

Alternative Options: No alternative options: If no action is taken, the roadway and other infrastructure constructions will not be completed.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/15/2024

255 (24-4245)

Contract Award

03/27/2025

88 (25-1463)

Contract Amendment for additional funds

08/26/2025

32 (25-5128)

Contract Amendment for extension of project term

12/11/2025

29 (25-7751)

Contract Amendment for additional funds and extension of project term

01/08/2026

35 (26-0186)

Contract Amendment for additional funds

03/19/2026

61 (26-1708)

Contract Amendment for additional funds

04/16/2026

49 (26-2311)

Contract Amendment for additional funds

 

Location:

Address (if applicable): 2201 Connorvale Road

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other                                     2601

$

$351,403.24

$351,403.24

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$351,403.24

$351,403.24

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$351,403.24

$351,403.24

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 7/9/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B