Harris County Logo
File #: 25-2173    Version: 1 Name:
Type: Negotiation Status: Passed
File created: 3/26/2025 In control: Commissioners Court
On agenda: 4/10/2025 Final action: 4/10/2025
Title: Request for approval to negotiate with Consor Engineers, LLC for Professional and Engineering services for the design of the Sam Houston Tollway North Pavement Surface Repairs design, bidding phase, and construction phase services (Precincts 1 & 3, MWBE Contracted Goal: 19.6%).

Primary Department: Toll Road Authority

Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Negotiation

 

Project ID (if applicable): N/A

Vendor/Entity Legal Name (if applicable): Consor Engineers, LLC

 

MWBE Contracted Goal (if applicable): 19.6%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to negotiate with Consor Engineers, LLC for Professional and Engineering services for the design of the Sam Houston Tollway North Pavement Surface Repairs design, bidding phase, and construction phase services (Precincts 1 & 3, MWBE Contracted Goal: 19.6%).

end

 

Background and Discussion:

Pavement surface on Sam Houston Tollway North is due for maintenance in the section that was installed in 2019. The existing surface is an asphalt Permeable Friction Course (PFC) which currently has a 5-8 year life cycle and is beginning to show signs of delamination.

 

Expected Impact:

Improved Conditions and life expectancy for the Roadway.

 

Alternative Options:

No other recommended option for this identified need.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any): N/A

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): N/A

Precinct(s): Precincts 1 & 3

 

Fiscal and Personnel Summary

Service Name

Engineering & Construction

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Revenue - TRA

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Revenue - TRA

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 4/10/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority

 

Attachments (if applicable): N/A