Legislation Details

File #: 24-7795    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 12/2/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval to execute an agreement with InfraTECH Engineers & Innovators, LLC in the amount of $111,308.00 for professional engineering services for a new traffic signal with pedestrian related appurtenances at the intersection of Barker Cypress Road at Coventry Park Drive, UPIN 24035MF3G501, Precinct 4, MWDBE Contracted Goal: 19.6%, MWDBE Current Participation: 0%.
Sponsors: Mony Hossain
Attachments: 1. 24-7795-Consultant-24035MF3G501 TS - Barker Cypress Rd at Coventry Park Dr - Infratech P4 12-10-2024

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN - 24035MF3G501

Vendor/Entity Legal Name (if applicable): InfraTECH Engineers & Innovators, LLC

 

MWDBE Contracted Goal (if applicable): 19.6%

MWDBE Current Participation (if applicable): 0%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with InfraTECH Engineers & Innovators, LLC in the amount of $111,308.00 for professional engineering services for a new traffic signal with pedestrian related appurtenances at the intersection of Barker Cypress Road at Coventry Park Drive, UPIN 24035MF3G501, Precinct 4, MWDBE Contracted Goal: 19.6%, MWDBE Current Participation: 0%.

end

 

Background and Discussion:

Traffic signals are constructed to improve the operation of an intersection and better facilitate pedestrian activities. As such, the consultant will be tasked with the signal design of the intersection and an evaluation of left turn storage to improve operations. The consultant will also be tasked with evaluating pedestrian accessibility through the provision of crosswalks and associated median nose opening adjustments required to facilitate pedestrian activities.

 

Expected Impact:

Designing and building a traffic signal at this intersection will improve operations and better facilitate pedestrian activities.

 

Alternative Options:

An alternative is to not build a signal at the intersection, which will not provide up to date operations and pedestrian benefits.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

8/6/2024

92

Approval of ATN.

 

Location:

Address (if applicable): Barker Cypress Road at Coventry Park Drive

Precinct(s): Precinct 4

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$111,308.00

$111,308.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$111,308.00

$111,308.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$111,308.00

$111,308.00

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: December 10, 2024

Anticipated Implementation Date (if different from Court date):

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Patrick Mandapaka, PhD, AICP, Director of Community Resilience &

Transportation Planning, HCED

 

Attachments (if applicable): Agreement