Title: Request for approval to purchase a certain tract for a negotiated price for Harris County Toll Road Authority for the public project known as Hardy Toll Road at Beltway 8 Interchange, tract number 428:11, for $9,082.00 which is $5,718.00 over the appraised value, UPIN 130505R131, Precinct 2.
Sponsors: Mony Hossain
Attachments: 1. 24-0427-NP- UPIN 130505R131- Hardy Toll Road at Beltway 8 Interchange - 1.30.2024

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Financial Authorization

 

Project ID : 130505R131

Vendor/Entity Legal Name: Any applicable landowner and/or property interest holder

 

MWDBE Contracted Goal (if applicable): Not Applicable

MWDBE Current Participation (if applicable): Not Applicable

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request for approval to purchase a certain tract for a negotiated price for Harris County Toll Road Authority for the public project known as Hardy Toll Road at Beltway 8 Interchange, tract number 428:11, for $9,082.00 which is $5,718.00 over the appraised value, UPIN 130505R131, Precinct 2.

end

 

Background and Discussion:

The Hardy Toll Road Sam Houston Parkway Direct Connector Projects will ultimately provide eight (8) direct connectors to improve freeway access between the two roadways. The construction of these direct connectors will accommodate the high volumes of traffic anticipated between Sam Houston Parkway (Beltway 8) and the Hardy Toll Road safely. The current connection between roadways, maintained by TxDOT, is depressed and floods in large rain events. Grade separated direct connectors between corridors offer the greatest efficiency, safety, capacity, and mobility for the traveling public. Phase I of the project will add three (3) new direct connectors to the existing eastbound to northbound direct connector, completing the western half of the interchange. The remaining direct connectors will be constructed in the future when warranted by traffic demands.  Acquisition of additional right-of-way (ROW) is necessary to accommodate the three (3) new direct connectors. The ROW to be acquired is a mix of industrial and commercial properties located along East and West Hardy Hardy Roads and along the Beltway 8 eastbound frontage road.

 

Expected Impact:

This project aligns with Harris County’s goals of providing accessible, affordable, equitable, reliable, safe, and sustainable transportation options and networks to facilitate efficient movement of people and goods throughout the region.

 

Alternative Options:

No other recommended solutions for this identified need.

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

6/6/2023

59

Public necessity

 

Location:

Address (if applicable): 0 Hardy Rd., Houston, TX 77032

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$9,082.00

$

$

Total Incremental Expenditures

$9,082.00

$

$

Funding Sources (do NOT write values in thousands or millions)

Administrative Approval Only - Funding Sources approval will be submitted at later date.

Other HCTRA

$9,082.00

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$9,082.00

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$9,082.00

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date: January 30, 2024

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

Contact(s) name, title, department: Trevor Smith, Interim Assistant Director, Real Property Division

Attachments (if applicable): Survey Map