Legislation Details

File #: 24-7494    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/24/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place (Phase II) Subdivision Drainage Improvements - 2018, with an addition in the amount of $114,307.76, Job No. 23/0178-1, UPIN 23208MF2TN01, Precinct 2, MWDBE Contracted Goal: 24%, MWDBE Current Participation: 100%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 23208MF2TN01 - Job No. 23/0178

Vendor/Entity Legal Name (if applicable): Reliance Construction Services, L.P.

 

MWDBE Contracted Goal (if applicable): 24%

MWDBE Current Participation (if applicable): 100%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place (Phase II) Subdivision Drainage Improvements - 2018, with an addition in the amount of $114,307.76, Job No. 23/0178-1, UPIN 23208MF2TN01, Precinct 2, MWDBE Contracted Goal: 24%, MWDBE Current Participation: 100%.

end

 

Background and Discussion:

The Beaumont Place Subdivision is located in the Greens Bayou watershed near Highway 90 and Beltway 8. The proposed improvements include roadside ditch regrading, driveway culvert upgrades, expansion of channel along Big Gulch, concrete lined Sulphur Gully channel with reinforced concrete box (RCB) crossing improvements. Improvements also include multiple detention ponds along Big Gulch with an extreme event overflow swale towards the upstream portion of the channel.

 

The Change in Contract includes the following:

 

•                     Quantity Adjustment: The addition of quantities reconciles actual quantities used in construction with the estimated quantities for completing the proposed scope of work. Items 5, 9, 17, 22, 23, 26, 30, 32, 37, 38, 40, 68, 114, 140, 142, 154, and 198 were increased for an addition in the amount of $228,408.52. Items 27, 141, and 143 were decreased for a deduction in the amount of $140,771.00.

 

•                     New Item 201 Reinforced Concrete Sidewalk and Item 202 Concrete Pavement (8”) were added for an addition in the amount of $26,670.24.

 

•                     The additions, deductions, and new items result in a net change in the amount of $114,307.76.

 

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Western Homes Addition subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

05/16/2023

23-2817

Transmittal by the Office of the Purchasing Agent of a project scheduled for advertisement for drainage improvements within the Beaumont Place Subdivision (2018) for Precinct 2 (230178).

06/27/2023

23-3607

Award - Construction Contract - Reliance Construction Services, L.P.

 

Location: Beaumont Place (Phase II) Subdivision, Houston, Texas

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

$114,307.76

$114,307.76

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$114,307.76

$114,307.76

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$114,307.76

$114,307.76

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: December 10, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC)