Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 21102MF1XE01
Vendor/Entity Legal Name (if applicable): Greater Northside Management District
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with the Greater Northside Management District in the amount of $682,430.00 for construction in connection with Sidewalk - Quitman Street - UPIN 21102MF1XE01, Precinct 2.
end
Background and Discussion:
This project will provide on-street bike lanes, and sidewalks along Quitman Street, from Houston Avenue to Elysian Street.
Expected Impact:
The project will improve mobility and community connectivity for residents and pedestrians.
Alternative Options:
If no action is taken, the project may experience delays in construction activities.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
05/25/2021 |
21-2292 |
Recommendation for authorization to execute an agreement with Greater Northside Management District for the purpose of funding and constructing improvements to Quitman Street, UPIN 21102MF1XE01, Precinct 2. |
Location:
Address (if applicable): Quitman Street from Houston Avenue to Elysian Street.
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
1070 - Mobility Fund |
$ 682,430.00 |
$ |
$ 682,430.00 |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ 682,430.00 |
$ |
$ 682,430.00 |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ 682,430.00 |
$ |
$ 682,430.00 |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: March 26, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Director of Disaster & Resiliency Division, Harris County Engineering Department
Attachments (if applicable): First Amendment To Interlocal Agreement For The Quitman Street Pedestrian, Bicycle, And Transit Project.