Legislation Details

File #: 26-3378    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 5/18/2026 In control: Commissioners Court
On agenda: 5/28/2026 Final action: 5/28/2026
Title: Request for approval of a temporary right of entry with San Jacinto River Authority, to gain access to conduct work on a detention basin project along Jackson Bayou (Jackson Bayou Watershed, Bond ID F-107, Project ID R500-01-00-E001, Agreement No. 2026-28, Precinct 3).

Primary Department: Flood Control District

Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable):                      

Vendor/Entity Legal Name (if applicable): San Jacinto River Authority

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a temporary right of entry with San Jacinto River Authority, to gain access to conduct work on a detention basin project along Jackson Bayou (Jackson Bayou Watershed, Bond ID F-107, Project ID R500-01-00-E001, Agreement No. 2026-28, Precinct 3).

end

 

Background and Discussion:

This agreement will provide temporary right-of-entry to the Flood Control District for construction of a stormwater detention basin along Jackson Bayou as part of the Flood Control District’s CDBG-DR program. This project reduces flood risk in the Jackson Bayou watershed and does not adversely impact downstream water surface elevations, adjacent properties outside of the proposed project limits, or receiving drainage infrastructure. This project occurs in the 2nd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

 

Expected Impact:

This agreement will provide temporary right-of-entry using property owned by the San Jacinto River Authority (SJRA) to the Flood Control District for construction of a stormwater detention basin.

 

Alternative Options:

The alternative to approving this item would be use the access from Runneburg Road on the south of the project area, which would result in additional traffic control measures and slower project delivery.

 

County Strategic Plan Goal:  5. Minimize the impact of climate change and disasters.

County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H2: Evaluate the feasibility and potential impacts of substantial, large-scale flood mitigation measures to provide equitable and transformational regional benefits.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/08/2026

132.

Approval to delegate authority to the Harris County Purchasing Agent to award construction contracts to the lowest responsible bidder for 29 identified Flood Control District projects, funded by the CDBG-DR and CDBG-MIT programs.

 

Location: The Jackson Bayou Stormwater Detention Basin project is located on the north side of Jackson Bayou (R100-00-00) and just north of Runneburg Road and to the west of the San Jacinto River Authority canal (see Exhibit 1).  This project also lies within the City of Crosby.

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

N/A

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Tax Revenue - FCD

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 5/28/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Attachments (if applicable): Agreement

Prepared by: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District

 

Briefing Information for Leadership

 

1.                     Project Scope: The Jackson Bayou Stormwater Detention Basin (SWDB) project site consists of excavating a wet-bottom stormwater detention basin bounded by Runneburg Road on the South, San Jacinto River Authority Canal (SJRA) on the East, and Sacred Heart Catholic Church and School on the West, within the City of Houston in Harris County, Texas. Major work activities include off-site disposal of approximately 33,000 cubic yards of excavation for a wet bottom stormwater detention basin. The stormwater detention basin construction will consist of clearing and grubbing the site, turf establishment, outfall pipes and overflow weir, floatables collection screen, wingwalls at the outfall pipe and site grading. Project will also include the removal and replacement of an existing roadway guard rail for construction access, removal and replacement of an existing outfall downstream of the basin, a temporary access road along the SJRA Canal, traffic control, and concrete rubble removal through the site

 

2.                     Project Benefits   This project reduces flood risk in the Jackson Bayou watershed and does not adversely impact downstream water surface elevations, adjacent properties outside of the proposed project limits, or receiving drainage infrastructure. The design removes inundation for 5 structures, reduces inundation depth for 16, clears 0.12 miles of roadway from flooding, and decreases the inundated area by 17.3 acres, resulting in a 0.07ft reduction in WSEL.

 

3.                     Bond ID and Bond Title (if applicable): Bond F-107; TX-GLO CDBG-DR Contract ID: 24-033-000-E072; US-HUD CDBG-DR Contract ID: B-17-DM-48-0001; B-18-DP-48-0001

 

4.                     Project Status: Construction contract has been awarded and tentative NTP is June 1, 2026

 

5.                     Time to complete construction: 90 days

 

6.                     Precinct and stakeholder involvement (if applicable): Project plans have been reviewed and approved by Harris County Engineering.

 

7.                     Prioritization score and quartile (if available): Click or tap here to enter text.

 

8.                     Is this project funded by a federal/state/local partnership, if so please specify (i.e., FEMA, CDBG, EPA, TWDB, City of Houston, etc.): CDBG

 

9.                     Any general discussion or background that should be mentioned: N/A