Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): Northpointe Blvd Segment 2 - 23/0411 - UPIN 20104MF1BQ01
Vendor/Entity Legal Name (if applicable): IEA Inc
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable):100%
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of an agreement with IEA Inc., in the amount of $90,054.38 for the Construction Phase Services of Northpointe Blvd Segment 2, from Northpointe Ridge Lane to Northpointe Terrace Drive, Job No. 23/0411, UPIN 20104MF1BQ01, Precinct 4, MWDBE Current Participation: 100%.
end
Background and Discussion:
This agreement is for the engineer of record, IEA Inc., to provide professional engineering services during the construction phase of Northpointe Blvd Segment 2.
Expected Impact:
This action item will allow the engineer of record to continue supporting the project through construction.
Alternative Options:
If no action is taken, the engineer of record will not be accessible for support through the construction of the project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
4/9/2019 |
1. f.1.26 |
Professional Services Agreement |
|
9/15/2020 |
1.i.9 |
PSA |
|
3/8/2022 |
98. |
Public Necessity |
|
5/10/2022 |
97. |
Study Report Approval |
|
11/29/2022 |
33. |
Public Necessity |
|
3/14/2023 |
75. |
Public Necessity |
Location:
Address (if applicable): Northpointe Blvd Segment 2, from Northpointe Ridge Lane to Northpointe Terrace Drive
Precinct(s): Precinct 4
|
Fiscal and Personnel Summary |
|
Service Name |
Road Construction Service |
|
|
FY 24 |
FY 25 |
Next 3 FYs |
|
Incremental Expenditures (do NOT write values in thousands or millions) |
|
Labor Expenditures |
$ |
$ |
$ |
|
Non-Labor Expenditures |
$90,054.38 |
$ |
$ |
|
Total Incremental Expenditures |
$90,054.38 |
$ |
$ |
|
Funding Sources (do NOT write values in thousands or millions) |
|
Existing Budget |
|
1070 - Mobility Fund |
$90,054.38 |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Total Current Budget |
$90,054.38 |
$ |
$ |
|
Additional Budget Requested |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
|
Total Additional Budget Requested |
$ |
$ |
$ |
|
Total Funding Sources |
$90,054.38 |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
|
Additional Positions Requested |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
Anticipated Court Date: 01/30/2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Dr. Hatem Elbastawisy, PE - (Interim) Senior Director of Project Delivery - Harris County Engineering Department
Attachments (if applicable): Letter, Award Documents