Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): 240043
Vendor/Entity Legal Name (if applicable): Gauge Engineering, LLC
MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval on the basis of highest overall evaluation and authorize negotiations with Gauge Engineering, LLC for professional architectural and/or engineering services for Friendswood Regional Stormwater Detention Basin for the Flood Control District, and the county, at its sole discretion, may discontinue negotiations and proceed to negotiate with the next ranking vendor(s) if unable to agree to an executable contract (240043), MWDBE Contracted Goal: 19.6%.
end
Background and Discussion:
The project area is approximately 105 acres in Southwestern Harris County within Precinct 2 inside the City of Friendswood limits at Clear Creek Watershed. The project is bounded by A100-00-00 on the south and west sides, FM 1959 on the north and by the Gulf Freeway on the east side. HCFCD and Harris County have free ownership or easement of all 105 acres of the project site area. The cultural resource survey has found site 41HR194 as an “Eligible” site for listing in the National Register of Historic Places (NRHP). No ground disturbing activities should occur within the boundary of 41HR194 without prior consultation with the Texas Historical Commission.
This project is the partnership project between the City of Friendswood, Galveston County, Galveston Consolidated Drainage District and Harris County Flood Control District. The overall objective of this project is to reduce the overall peak flows and decrease the water surface elevation along Clear Creek Channel (A100-00-00). Three alternatives were evaluated during the PER phase and alternative 2 is selected as a recommended alternative. Alternative 2 is a dry bottom basin with a total area of 70 acres that avoids the jurisdictional wetlands and eligible National Register of Historic Place Site. It provides total 710 acre-feet of storage volume.
Expected Impact:
The alternative 2 removed 87 flooded structures, removed 97 acres inundation area and 0.7 miles inundation roadways from the floodplain for a 100-year level of service.
Alternative Options:
The alternative option does not proceed to the final design phase of this project. Flood risk in the project area would remain the same.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
10/11/2022 |
310 |
Agreement with City of Friendswood, Galveston County and Galveston Consolidated Drainage District |
|
11/15/2022 |
142 |
Agreement with McDonough Engineering Corporation for PER Service |
|
3/26/2024 |
381 |
Advertisement |
Location: HCFCD Unit A500-09-00-E001
Address (if applicable): At the intersection of Dixie Farm Road and Blackhawk Blvd
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 6/13/2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Pooja Bhatta, Project Manager, Capital Projects South Department. Kenneth Jackson, Senior Buyer, Purchasing.