Legislation Details

File #: 24-4544    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/19/2024 In control: Commissioners Court
On agenda: 8/6/2024 Final action: 8/6/2024
Title: Request for approval of a change in contract with Precise Services, Inc., in connection with Parkway Forest Subdivision Drainage Improvements - 2018, Job No. 23/0238-2, UPIN 19101MF14P01, Precinct 1, MWDBE Contracted Goal: 31%, MWDBE Current Participation: 100%.
Sponsors: Mony Hossain

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN 19101MF14P01; Job No: 23/0238

Vendor/Entity Legal Name (if applicable): Precise Services, Inc.

 

MWDBE Contracted Goal (if applicable): 31%

MWDBE Current Participation (if applicable): 100%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Precise Services, Inc., in connection with Parkway Forest Subdivision Drainage Improvements - 2018, Job No. 23/0238-2, UPIN 19101MF14P01, Precinct 1, MWDBE Contracted Goal: 31%, MWDBE Current Participation: 100%.

end

 

Background and Discussion:

Parkway Forest is in Northeast Harris County, Texas, Precinct 1. The subdivision is mainly composed of single-family homes. The residents have experienced structural flooding during several recent flood events. The purpose of this project is to reduce flooding in the subdivision. The proposed solution includes upgrading storm sewers and adding a detention pond.

 

The change in contract includes the following:

 

•                     Repairs to existing water line: Change in construction scope adding new line item due to the need of emergency repair to an existing water main line that was damaged because it was not shown on plans for an additional cost of $3,498.90 and 0 days.

•                     Repairs to existing ROW conditions: Additional quantities to replace existing damaged B-B inlet and the surrounding compromised pavement with an additional cost of $31,381.00 and 0 days.

•                     Water table conflict: Change in construction scope adding new line items and modifying quantities of the scope of work due to water table elevation conflict with construction process for a deduction in the amount of ($34,879.90) and 0 days.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Parkway Forest subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the original scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/29/2023

23-4987

Contract - Award

06/25/2024

24-3639

Contract - Amendment

 

Location: Parkway Forest Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date:  August 6, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Change in Contract (CIC)