Legislation Details

File #: 26-3250    Version: 1 Name:
Type: Commercial Paper Status: Passed
File created: 5/7/2026 In control: Commissioners Court
On agenda: 5/14/2026 Final action: 5/14/2026
Title: Request by the Office of Management and Budget for approval of commercial paper funding for Universal Services for the Infrastructure Enhancements Replacement project in the additional amount of $830,000 for a total CP funding of $18,770,000.

Primary Department: Management and Budget

Primary Department Head/Elected Official: Daniel Ramos, Executive Director

 

Secondary Department: Universal Services

Secondary Department Head/Elected Official: Sindhu Menon, Executive Director & CIO

 

Regular or Supplemental RCA: Supplemental RCA

Type of Request: Commercial Paper

 

Project ID (if applicable): NI008

Vendor/Entity Legal Name (if applicable): N/A

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request by the Office of Management and Budget for approval of commercial paper funding for Universal Services for the Infrastructure Enhancements Replacement project in the additional amount of $830,000 for a total CP funding of $18,770,000.

end

 

Background and Discussion:

Commercial Paper Series A-1 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

 

Commercial Paper is being requested for the Infrastructure Enhancements Replacement project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means, or pay-as-you-go sources.  This is for approval for allocation of commercial paper for a previously approved project within the previously authorized amount.

 

HB 1869 compliance confirmed by: Paige Abernathy, Assistant County Attorney, September 10, 2024.

 

 

 

Expected Impact:

This project will enhance the usage of PeopleSoft across Harris County. There are two key focus areas for this project: 1) Automation and Efficiency; and 2) Enhanced Reporting and Analytics.

 

Automation and Efficiency will focus on automating the manual interfaces for the business. Enhanced Reporting and Analytics will build out the reports and functionality in PeopleSoft to ensure departments have easy access to the data and functionality they need.

 

Alternative Options:

No alternatives have been identified for this project.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  Choose an item.

Infrastructure Initiative (Goal 2):  Choose an item.

Economy Initiative (Goal 3): Choose an item.

Health Initiative (Goal 4): Choose an item.

Climate/Resilience Initiative (Goal 5): Choose an item.

Housing Initiative (Goal 6): Choose an item.

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/31/2018

4.j.2

Request for approval of commercial paper funding for $870,000 - Phase 2 (Series A-1)

10/29/2019

6.b

Project authorization

11/12/2019

4.g.4

Request for approval of commercial paper funding for $3,775,000 (Series A-1)

10/27/2020

5.b.2

Project authorization

11/10/2020

4.g.3

Request for approval of commercial paper funding for $3,800,000 (Series A-1)

03/09/2021

21-718

Project authorization

08/24/2021

21-4291

Request for approval of commercial paper funding for $4,000,000 (Series A-1)

01/25/2022

22-0644

Request for approval of commercial paper funding for $1,940,000 (Series A-1)

03/08/2022

22-1699

Request for SFY22 authorization of $1,398,000

09/13/2022

22-5423

Request for an additional incremental authorization of $440,000, FY23 total authorization of $1,344,000

10/18/2022

22-6592

Request for approval of commercial paper funding for $440,000. (Series A-1)

08/08/2023

23-4371

Request for approval of the Final Investment Memo for the Infrastructure Enhancements & Replacements project for an additional incremental authorization of $645,000 for FY 2024.

10/10/2023

23-5835

Request for approval of commercial paper funding for $645,000. (Series A-1)

10/08/2024

24-6283

FIM an additional project authorization of $1,469,338 for a total authorization of $1,732,500 in FY 2025.

5/22/2025

25-3014

Request for approval of commercial paper funding for $1,470,000. (Series A-1)

8/26/2025

25-5184

Request for an incremental authorization of $1,827,000 and commercial paper funding in the amount of $1,000,000. (Series D)

 

Location: N/A

Address (if applicable):

Precinct(s): Choose an item.

 

Fiscal and Personnel Summary

Service Name

Infrastructure Enhancements Replacement

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Commercial Paper

$

$830,000

$830,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$830,000

$830,000

$

Total Funding Sources

$

$830,000

$830,000

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 5/14/2026

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Fahad Gulzar, Acting Deputy Executive Director, Office of Management and Budget

 

Attachments (if applicable): N/A