Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 21102MF1QB01
Vendor/Entity Legal Name (if applicable): Frost Construction Co., Inc.
MWBE Contracted Goal (if applicable): 16%
MWBE Current Participation (if applicable): 16.38%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): 0
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Frost Construction Co. Inc. in connection with 15430 East Freeway 'IH-10E' - East Harris County Healthcare and Social Services Hub - 2024, adding 5 calendar days, with an addition in the amount of $16,169.77, UPIN 21102MF1QB01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 16.38%.
end
Background and Discussion:
East Harris County Healthcare & Social Services Hub is a 10,650 square foot building that will provide wrap-around healthcare and social services for the East Harris community. This new facility will be located at 15430 East Fwy, Channelview, TX 77530. The project is primarily funded through CDBG-DR with matching funds from Precinct 2 & Public Health. Change Order includes:
1)Changes from PR-005, which include the addition of an ADA compliant handrail, a case opening, and MEP infrastructure to support a walk-in cooler.
2)Removal of cabinets in Room 120. Drawings showed casework, where the program is planning placing furniture in this location.
Expected Impact:
Upon completion, this project will significantly improve the operations and efficiency of service to Harris County Precinct Two Community. This change order will ensure the new building will be placed on a surface that has not impacted by any existing structures and extend the longevity of the building footprint.
Alternative Options:
Commissioner court could postpone the change order, which would postpone payment to the Contractor.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan:
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
10/16/2025 |
47 |
Request for approval of a change in contract with Frost Construction Co. Inc., in connection with 15430 East Freeway 'IH-10E' - East Harris County Healthcare and Social Services Hub - 2024, with an addition in the amount of $6,495.43, UPIN 21102MF1QB01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 16.90%. |
|
9/18/2025 |
44 |
Request for approval of a change in contract with Frost Construction Co. Inc. in connection with 15430 East Freeway 'IH-10E' - East Harris County Healthcare and Social Services Hub - 2024, adding 20 calendar days, with an addition in the amount of $219,552.70, UPIN 21102MF1QB01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 16%. |
|
3/27/2025 |
94 |
Request for approval of a change in contract with Frost Construction Co. Inc. in connection with 15430 East Freeway 'IH-10E' - East Harris County Healthcare and Social Services Hub - 2024, adding 30 calendar days, with an addition in the amount of $25,620.75, UPIN 21102MF1QB01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 16%. |
|
10/29/2024 |
44 |
Request for approval of a change in contract with Frost Construction Co., Inc., in connection with 15430 East Freeway 'IH-10E' - East Harris County Healthcare and Social Services Hub - 2024, adding 78 calendar days, with an addition in the amount of $379,738.75, UPIN 21102MF1QB01, Precinct 2, MWDBE Contracted Goal: 16%, MWDBE Current Participation: 16%. |
|
8/27/2024 |
58 |
Request for approval of a change in contract with Frost Construction Co. Inc., in connection with East Harris County Healthcare and Social Services Hub, adding nine calendar days, with an addition in the amount of $155,795.29, Job No. 23/0309-1, UPIN 21102MF1QB01, Precinct 2, MWDBE Contracted Goal: 16%, MWDBE Current Participation: 16%. |
|
10/31/2023 |
315 |
Request for approval of an award on the basis of low bid to Frost Construction Company, Inc. in the amount of $4,557,000 for construction of the East Harris County Health & Social Services Facility Hub in Precinct 2, and for the County Clerk to execute any applicable bonds to be received (230309), MWDBE Contracted Goal: 16%. |
Location:
Address (if applicable): 15430 East Freeway, Channelview, TX 77530
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Grant GLO/HUD |
$ |
$16,169.77 |
$16,169.77 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$16,169.77 |
$16,169.77 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$16,169.77 |
$16,169.77 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 4/30/2026
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services
Attachments (if applicable): Change Order Form