Legislation Details

File #: 25-5590    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/29/2025 In control: Commissioners Court
On agenda: 9/18/2025 Final action: 9/18/2025
Title: Request for approval of a change in contract with WadeCon, LLC, in connection with final construction of Timber Forest Drive; Bridge Over UPRR; 2018, with an addition in the amount of $85,821.04, Job No. 20/0284-5, UPIN 19101MF12701, Precinct 3, Justification for 0% MWBE Participation Goal: (project was awarded prior to launch of County's M/WBE Program).

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

 

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 20/0284, UPIN 19101MF12701

Vendor/Entity Legal Name (if applicable): WadeCon, LLC

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with WadeCon, LLC, in connection with final construction of Timber Forest Drive; Bridge Over UPRR; 2018, with an addition in the amount of $85,821.04, Job No. 20/0284-5, UPIN 19101MF12701, Precinct 3, Justification for 0% MWBE Participation Goal: (project was awarded prior to launch of County’s M/WBE Program).

... end

 

Background and Discussion:

Project includes the construction of a new bridge over the UPRR tracks with roadway approaches, medians and

Sidewalks

 

PCO#10 - FINAL ADJUSTMENT: This change in contract includes the final reconciliation of actual quantities used in construction against the bid quantities.  $85,821.04

 

Expected Impact:

Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated for

the work performed

 

Alternative Options:

Continue with the original plan.

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/10/2020

21.d.8.q

Contract Award

07/20/2021

106 (21-3649)

Contact Amendment #1 for extension of project term

10/26/2021

54 (21-5644)

Contact Amendment #2 for extension of project term

10/18/2022

38 (22-6508)

Contact Amendment #3 for extension of project term and additional funds

09/19/2023

57 (23-5342)

Contract Amendment #4 for extension of project term and additional funds

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund                     

$

$85,821.04

$85,821.04

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$85,821.04

$85,821.04

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$85,821.04

$85,821.04

$

Grants – Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget:

Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request:

Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 9/18/2025

Anticipated Implementation Date (if different from Court date):  N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architecture Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B