Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Financial Authorization
Project ID (if applicable): 23050MF2P701
Vendor/Entity Legal Name (if applicable): Any applicable landowner and/or property interest holder
MWDBE Contracted Goal (if applicable): Not Applicable
MWDBE Current Participation (if applicable): Not Applicable
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to purchase a certain tract for a negotiated price for the Harris County Toll Road Authority for the public project known as Sam Houston Tollway East/SH225 Direct Connector, tract 5, for $75,000.00 which is $46,037.00 over the appraised value, UPIN 23050MF2P701, Precinct 2.
end
Background and Discussion:
The Sam Houston Tollway East / State Highway (SH) 225 Direct Connector Project will ultimately add eight
direct connectors to improve freeway access between the two roadways. Existing ramp access to/from the
freeway and adjacent, SH 225 frontage roads will be adjusted in accordance with the approved schematic.
Acquisition of additional right-of-way (ROW) is necessary to accommodate the adjustments. The ROW to be
acquired is a mix of industrial and commercial properties located on the SH225 frontage Road between
Northbound Sam Houston Tollway and Deerwood Glen Drive. The parcel is needed to support the direct connector overpass construction that is included with the project.
Expected Impact:
This project aligns with Harris County’s goals of providing accessible, affordable, equitable, reliable, safe and
sustainable transportation options and networks to facilitate efficient movement of people and goods
throughout the region.
Alternative Options:
No other recommended solutions for this identified need.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
2/21/2023 |
82 |
Public Necessity |
Location:
Address (if applicable): 3940 Pasadena Fwy., Pasadena, Texas 77503
Precinct(s): Precinct 2
Fiscal and Personnel Summary |
Service Name |
|
|
FY 24 |
FY 25 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$ 75,000.00 |
$ |
$ |
Total Incremental Expenditures |
$ 75,000.00 |
$ |
$ |
Funding Sources (do NOT write values in thousands or millions) |
Administrative Approval Only - Funding Sources approval will be submitted at later date. |
Other -HCTRA |
$ 75,000.00 |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$ 75,000.00 |
$ |
$ |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$ 75,000.00 |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: November 14, 2023
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Trevor Smith, Interim Assistant Director, Real Property Division
Attachments (if applicable): Survey Map