File #: 25-2646    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/23/2025 In control: Commissioners Court
On agenda: 5/8/2025 Final action: 5/8/2025
Title: Request for approval of a change in contract with ECM Construction, LLC, in connection with Sidewalk - North Eldridge Parkway - 2022, adding 14 calendar days, with an addition in the amount of $14,235.00, Job. No. 24/0224-1, UPIN 23103MF2RP01, Precinct 3, MWBE Contracted Goal: 13.05%, MWBE Current Participation: 100%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0224, UPIN 23103MF2RP01

Vendor/Entity Legal Name (if applicable): ECM Construction, LLC

 

MWBE Contracted Goal (if applicable): 13.05%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with ECM Construction, LLC, in connection with Sidewalk - North Eldridge Parkway - 2022, adding 14 calendar days, with an addition in the amount of $14,235.00, Job. No. 24/0224-1, UPIN 23103MF2RP01, Precinct 3, MWBE Contracted Goal: 13.05%, MWBE Current Participation: 100%.

end

 

Background and Discussion:

This project involves the construction of sidewalks along North Eldridge Parkway from Spencer Road (FM 529) to West Road, and along West Road from North Eldridge Parkway to 940 feet East (Precinct 3).

 

This change order involves adding a missing item to the contract, increasing the current contract value by $14,235.00 to ensure the project is completed as originally intended.

 

Item to be added:

PCO #1     Borrow Material, Cost: $14,235.00, Additional Days:  14

365 CY x $39/CY = $14,235.00

 

 

Expected Impact:

Improving the pedestrian facilities will ensure reliable and safe route of transportation to residents of the Harris County.

 

Alternative Options:

The alternative will be not to construct the proposed sidewalk where borrow material is needed.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/27/2024

288 (24-5215)

Contract Award

 

Location:

Address (if applicable): 

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 2601

$

$14,235.00

$14,235.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$14,235.00

$14,235.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$14,235.00

$14,235.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 5/8/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable):  County Auditor’s Form 1258B