Skip to main content
Harris County Logo
File #: 25-4446    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/9/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of a change in contract with D&W Contractors, Inc., in connection with Wallisville Road - from 965' West of Garth Road to 1,400' West of North Main Street - 2017, with an addition in the amount of $5,000.00, Job No. 23/0225-4, UPIN 18102MF0S601, Precinct 3, MWBE Contracted Goal: 29%, MWBE Current Participation: 44.02%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0225, UPIN 18102MF0S601

Vendor/Entity Legal Name (if applicable): D&W Contractors, Inc.

 

MWBE Contracted Goal (if applicable): 29%

MWBE Current Participation (if applicable): 44.02%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with D&W Contractors, Inc., in connection with Wallisville Road - from 965’ West of Garth Road to 1,400’ West of North Main Street - 2017, with an addition in the amount of $5,000.00, Job No. 23/0225-4, UPIN 18102MF0S601, Precinct 3, MWBE Contracted Goal: 29%, MWBE Current Participation: 44.02%.

end

 

Background and Discussion:

The project includes reconstruction of Wallisville Road - from 965 feet west of Garth Road to 1,400 feet west of North Main Street.  Reconstruction includes an upgrade of the roadway from a two-lane asphalt road with open ditches to a 4-lane concrete curb and gutter boulevard with a 32' raised median.


This change in contracts includes:

                     PCO #17 (RFI #74): Installation of a modified Type C drop inlet at Station 10+17 to capture flow from an off-site swale.  Cost $5,000.00

 

Expected Impact:

This change is to compensate the contractor for performing necessary work required to ensure proper drainage.

 

Alternative Options:

There is no alternative for as this is required for proper drainage.

 

 

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

08/08/2023

272 (23-4489)

Contract Award

04/23/2024

62 (24-2115)

Contract Amendment #1 for additional funds and extension of project term

03/27/2025

109 (25-2034)

Contract Amendment #2 for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund

$

$5,000.00

$5,000.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$5,000.00

$5,000.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$5,000.00

$5,000.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/7/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B