Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): B513-02-00-E003 and L500-10-00-E002
Vendor/Entity Legal Name (if applicable): N/A
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of a consent to assignment to LJA Engineering, Inc., of the rights and obligations of McDonough Engineering Corporation, under agreements with the Flood Control District (Armand Bayou Watershed and Little Cypress Creek Watershed, Bond IDs F-72 and F-31, Project IDs B513-02-00-E003 and L500-10-00-E002, Agreement Nos. 2022-57 and 2019-80, Countywide).
end
Background and Discussion:
The Flood Control District has existing agreements with McDonough Engineering Corporation to provide engineering services for the Baywood Stormwater Detention Basin and the Mueschke West Stormwater Detention Basin. McDonough Engineering Corporation was purchased by LJA Engineering, Inc.
Expected Impact:
Continue engineering services with the existing agreements.
Alternative Options:
If the consent to assignment is not approved, the Flood Control District will not be able to complete work under the existing agreements.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
09/14/2021 |
137. |
Agreement |
03/26/2019 |
2.a.13 |
Agreement |
10/09/2018 |
2.c.5 |
ATN |
08/28/2018 |
2.b.9 |
ATN |
Location: N/A
Address (if applicable):
Precinct(s): Countywide
Fiscal and Personnel Summary |
Service Name |
N/A |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: September 19, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Yesenia Martinez, Commissioners Court Coordinator, Flood Control District
Attachments (if applicable): Agreement