Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 19101MF14P02
Vendor/Entity Legal Name (if applicable): CenterPoint Energy
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Utility Agreement with CenterPoint Energy for Streetlight Rehab in connection with Parkway Forest Subdivision Drainage Improvements - 2018 (P122-00-00 Basin), UPIN 19101MF14P02, Precinct 1.
end
Background and Discussion:
The Parkway Forest Subdivision Drainage Improvements - 2018 (P122-00-00 Basin) is located in Northeast Harris County in Precinct 1. The proposed solution includes upgrading the storm sewer system and adding a detention basin.
This rehab is located on Pearl Point Street, south of Abalone Way. The existing streetlight (ID 331844) conflicts with the proposed design. As outlined in the utility agreement, the scope of work includes the temporary removal of the streetlight during construction, followed by its reinstallation once construction is complete and verified. The streetlight will be restored to its original location and electrically reconnected.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Parkway Forest community. No impact on project schedule or cost anticipated.
Alternative Options:
If no action is taken, the project may not be constructed as scoped.
County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H6: Expand neighborhood drainage programs.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan:
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
|
|
|
Location: Parkway Forest Subdivision
Address (if applicable): N/A
Precinct(s): Precinct 1
Fiscal and Personnel Summary |
Service Name |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Existing Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Sources |
$ |
$ |
$ |
$ |
Grants - Proposed Budget (For Grants Items only) |
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 8/7/2025
Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.
Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services
Attachments (if applicable): Contract