File #: 26-5478    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/12/2026 In control: Commissioners Court
On agenda: 8/25/2026 Final action: 8/25/2026
Title: Request for approval of a change in contract with CE Barker LTD, in connection with HCSFNC - TO3 - Ella Boulevard Providence Place Habitat for Humanity, adding 157 calendar days, with an addition in the amount of $335,148.14, Job No. 23/0434-3, UPIN 20035MF1J501, Precinct 1, MWBE Contracted Goal: 25%, MWBE Current Participation: 31.62%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0434, UPIN 20035MF1J501

Vendor/Entity Legal Name (if applicable): CE Barker LTD

 

MWBE Contracted Goal (if applicable): 25%

MWBE Current Participation (if applicable): 31.62%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with CE Barker LTD, in connection with HCSFNC - TO3 - Ella Boulevard Providence Place Habitat for Humanity, adding 157 calendar days, with an addition in the amount of $335,148.14, Job No. 23/0434-3, UPIN 20035MF1J501, Precinct 1, MWBE Contracted Goal: 25%, MWBE Current Participation: 31.62%.

end

 

Background and Discussion:

In response to the destruction brought by Hurricane Harvey that underscored critical shortages in Harris County’s inventory of affordable homes, Harris County’s Single Family New Construction Program (SFNC) matches individuals and families with opportunities to purchase new affordable homes in growing development throughout the County. Contract allows for the construction of infrastructure such as water, sanity, drainage and some landscape features.

 

Change order includes the following items:

 

                     The increase of quantities for line item numbers 26, 54, 59, 60, 62, 63, 64, 65, 67, 104 for an addition in the amount of $153,212.90.

                     The decrease of quantities for line item numbers 57 and 66 for a deduction in the amount of $152.83.

 

New Line Item:

 

                     Added new line item number 118 - Driveways, ADA Ramp, RCP & SET for an addition in the amount of $39,506.07 and 14 days.

                     Added new line item number 119 - 8” gate valve and Box 9’ extension for an addition in the amount of $17,816.00.

                     Added new line item number 112 - Construction of Additional Fire water line installation for an addition in the amount of $124,766.00 and 75 days.

                     Addition of 68 days due to additional tasks and unforeseen circumstances.

 

The above additions and deduction result in an addition in the amount of $335,148.14 and 157 calendar days.

 

The project is substantially completed, but as per the Harris County Housing Department’s request and Harris County Management’s approval, there will be additional work that was not included in the original contract. Due to this added scope, the final completion date is still unknown. Once the new budget is added, we will prepare the final change order with all the expected dates included.

 

Expected Impact:

Construction of infrastructure will allow a new single family residential community of approximately 60 single family residential home to be constructed on approximately 10.57 acres in Precinct 1 under the Harris County Single-Family New Construction Program. Changes will allow for the project to be constructed per the original intent.

 

Alternative Options:

No other options, the proposed infrastructure is needed to complete the project.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: U: Build and preserve affordable housing, particularly for low-income families.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  I4: Encourage the growth of natural habitats in County channels and improve cleanliness of green spaces while reducing debris and enhancing beautification.

Economy Initiative (Goal 3): J2: Increase the strength and size of MWBE prime vendors.

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): U1: Develop community housing plan and dashboard.

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/14/2023

282 (23-6659)

Transmittal - Advertisement

01/09/2024

271 (24-0287)

Contract Award - CE Barker Ltd.

08/07/2025

68 (25-4549)

Contract Amendment (23/0434-01) for additional funds and extension of project term

10/16/2025

31 (25-6159)

Contract Amendment (23/0434-02) for additional funds and extension of project term

 

Location: Providence Gardens

Address (if applicable):

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 2601

$

$335,148.14

$335,148.14

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$335,148.14

$335,148.14

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$335,148.14

$335,148.14

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 8/25/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B