File #: 25-3437    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/27/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of a change in contract with GLM Contracting, Inc., in connection with final construction of Intersection Improvements - Mason Road at Cypresswood Drive - 2021, adding 84 calendar days, with an addition in the amount of $24,346.60, Job No. 22/0019-2, UPIN 221033010230015, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 31.81%.

Primary Department: County Engineer

Primary Department Head/Elected Official:  Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Financial Authorization

 

Project ID (if applicable): Job No. 22/0019, UPIN 221033010230015

Vendor/Entity Legal Name (if applicable): GLM Contracting, Inc.

 

MWBE Contracted Goal (if applicable): 19%

MWBE Current Participation (if applicable): 31.81%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with GLM Contracting, Inc., in connection with final construction of Intersection Improvements - Mason Road at Cypresswood Drive - 2021, adding 84 calendar days, with an addition in the amount of $24,346.60, Job No. 22/0019-2, UPIN 221033010230015, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 31.81%.

end

 

Background and Discussion:

Expanding turn-lane capacity and installing a new mast arm assembly aims to address congestion and improve safety on the southbound, westbound, and northbound approaches.  Proper planning around design details-such as storage lengths, tapers, mast arm sizing, and signal phasing-will be critical to ensure these improvements deliver the intended operational and safety benefits.

 

Expected Impact:

Overall, the enhancements aim to boost efficiency and safety at this intersection, lowering travel times and mitigating congestion for the foreseeable future.

 

Alternative Options:

No change to current layout

 

 

 

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

07/15/2024

220 (24-4236)

Contract Renewal

01/09/2025

46 (25-0219)

Contract Amendment #1 for additional funds

 

Location:

Address (if applicable):

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other                                                3109

$

$24,346.60

$24,346.60

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$24,346.60

$24,346.60

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$24,346.60

$24,346.60

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/12/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 