File #: 25-7038    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/22/2025 In control: Commissioners Court
On agenda: 10/30/2025 Final action: 10/30/2025
Title: Request by the Toll Road Authority for approval of a second amendment with Ship Channel Constructors, LLC, a limited liability company the members of which are Traylor Bros., Inc. and Zachry Construction Corporation, for construction of the ship channel bridge replacement project to increase the contract value by a not-to-exceed amount of $173,400,000 and to update necessary contract documents associated with this amendment (Precinct 2).

Primary Department: Toll Road Authority

Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Supplemental RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 17/0028 / Contract 345

Vendor/Entity Legal Name (if applicable): Ship Channel Constructors, LLC

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal not applicable to request

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request by the Toll Road Authority for approval of a second amendment with Ship Channel Constructors, LLC, a limited liability company the members of which are Traylor Bros., Inc. and Zachry Construction Corporation, for construction of the ship channel bridge replacement project to increase the contract value by a not-to-exceed amount of $173,400,000 and to update necessary contract documents associated with this amendment (Precinct 2).

end

 

Background and Discussion:

On November 17, 2021, Commissioners Court approved First Amendment of construction contract with Ship Channel Constructors, LLC (SCC) for the construction of the Sam Houston Tollway Ship Channel Bridge replacement project over the Houston Ship Channel. 

 

A Second Amendment with SCC is necessary to update the contract value and contract documents to accommodate the updated ship channel bridge main span design needed to complete performance of the amended agreement.

 

Expected Impact:

Approval of the contract amendment will allow SCC to continue with construction of the ship channel bridge.

 

 

Alternative Options:

No other recommended options.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):   N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

01/09/2018

21.d.10.d

Court approval of low bid construction contract with SCC

11/30/2021

96

Court approval of First Amendment with SCC

 

Location:

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering & Construction Service

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Revenue - TRA

$

$82,500,000

$82,500,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$82,500,000

$82,500,000

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$82,500,000

$82,500,000

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 10/30/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority

 

Attachments (if applicable): Second Amendment