Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Supplemental RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 17/0028 / Contract 345
Vendor/Entity Legal Name (if applicable): Ship Channel Constructors, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request by the Toll Road Authority for approval of a second amendment with Ship Channel Constructors, LLC, a limited liability company the members of which are Traylor Bros., Inc. and Zachry Construction Corporation, for construction of the ship channel bridge replacement project to increase the contract value by a not-to-exceed amount of $173,400,000 and to update necessary contract documents associated with this amendment (Precinct 2).
end
Background and Discussion:
On November 17, 2021, Commissioners Court approved First Amendment of construction contract with Ship Channel Constructors, LLC (SCC) for the construction of the Sam Houston Tollway Ship Channel Bridge replacement project over the Houston Ship Channel.
A Second Amendment with SCC is necessary to update the contract value and contract documents to accommodate the updated ship channel bridge main span design needed to complete performance of the amended agreement.
Expected Impact:
Approval of the contract amendment will allow SCC to continue with construction of the ship channel bridge.
Alternative Options:
No other recommended options.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
01/09/2018 |
21.d.10.d |
Court approval of low bid construction contract with SCC |
|
11/30/2021 |
96 |
Court approval of First Amendment with SCC |
Location:
Address (if applicable): N/A
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering & Construction Service |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Revenue - TRA |
$ |
$82,500,000 |
$82,500,000 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$82,500,000 |
$82,500,000 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$82,500,000 |
$82,500,000 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 10/30/2025
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item
Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority
Attachments (if applicable): Second Amendment