File #: 25-4640    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 7/23/2025 In control: Commissioners Court
On agenda: 8/7/2025 Final action: 8/7/2025
Title: Request for approval of an amendment to an agreement with PGAL, Inc. in the amount of $327,690.00 for Professional Architecture and Engineering Services related to the Various Locations - Downtown Facilities Masterplan - 2024, UPIN 24035MF3JF01, Precinct 1, Justification for 0% MWBE Participation Goal: 0% - Specialized, Technical, or Unique in Nature.
Sponsors: Mony Hossain
Attachments: 1. 25-4640-CIC-UPIN-24035MF3JF01-DowntownMasterplan-PGAL.pdf

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP. CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 24035MF3JF01

Vendor/Entity Legal Name (if applicable): PGAL, Inc.

 

MWBE Contracted Goal (if applicable): 0%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  0% - Specialized, Technical, or Unique in Nature

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of an amendment to an agreement with PGAL, Inc. in the amount of $327,690.00 for Professional Architecture and Engineering Services related to the Various Locations - Downtown Facilities Masterplan - 2024, UPIN 24035MF3JF01, Precinct 1, Justification for 0% MWBE Participation Goal:  0% - Specialized, Technical, or Unique in Nature.

end

 

 

Background and Discussion:

On April 15, 2025, the Office of the County Engineer (OCE) convened a project kick-off meeting with all relevant Harris County downtown stakeholders to formally launch the Downtown Masterplan (DMP) initiative. Thirty-two (32) departments have been identified as impacted stakeholders. Each department is actively participating in the data collection process to assess their current space utilization and forecast future departmental requirements over the next five (5), ten (10), and twenty (20) years.

 

The DMP aims to deliver a comprehensive, data-driven plan for optimizing Harris County’s real estate assets in the downtown campus. The consultant will provide professional services that include data validation, needs assessments, scenario modeling, strategic space planning, risk analysis, and phased implementation strategies.

 

The amended scope reflects a streamlined and focused approach, reducing the original proposed contract value from $507,120.00 to $327,690.00. This cost-effective adjustment preserves all essential planning functions required to complete a high-quality master plan while limiting optional services to only those deemed necessary for the project’s success.

 

 

Expected Impact:

The Downtown Masterplan will identify, address, and provide recommendations for various space needs for the different county facilities and staff working in the Downtown Area.

 

Alternative Options:

The alternate option is to continue addressing issues regarding space needs for Harris County Downtown Facilities as they arise without planning and assessment tools in place to mitigate future issues.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H4: Consistently embed sustainability considerations in the project planning and design process.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: No additional notes.

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/19/2024

429 (24-6012)

Approval to Negotiate

01/09/2025

126 (25-0379)

Approval of Agreement

 

 

 

 

 

 

 

Location: Downtown Houston

Address (if applicable): N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 1035 facilities funding

$

$327,690.00

$327,690.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$327,690.00

$327,690.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$327,690.00

$327,690.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 8/7/2025

Anticipated Implementation Date (if different from Court date): Click or tap to enter a date.

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Michael Ware, Director of Real Property, Office of the County Engineer

 

Attachments (if applicable):