File #: 25-0093    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/23/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 22 calendar days, with an addition in the amount of $35,206.00, Job No. 21/0309-17, UPIN 20101MF1ET01, Precinct 1, MWBE Contracted Goal: 17%, MWBE Current Participation: 29.63%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP County Engineer

 

Secondary Department: Commissioner, Precinct 1

Secondary Department Head/Elected Official: Rodney Ellis

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): 21/0309

Vendor/Entity Legal Name (if applicable): Brookstone, LP

 

MWBE Contracted Goal (if applicable): 17%

MWBE Current Participation (if applicable):29.63%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 22 calendar days, with an addition in the amount of $35,206.00, Job No. 21/0309-17, UPIN 20101MF1ET01, Precinct 1, MWBE Contracted Goal: 17%, MWBE Current Participation: 29.63%.

end

 

Background and Discussion:

 

Harris County Precinct One Administration Office and Service Center is a new two-story, approximately 37,000 sf building located at 2787 El Camino Street. The building will house the administrative leadership departments that serve the needs of the surrounding Harris County Precinct One community, and a well-equipped Multi-purpose Center that will accommodate the needs of the Precinct and its constituents.

 

This change in contract includes scope changes to the building interior and exterior based on COH permit approval and fire marshal requirements; and 22 additional calendar days to extend substantial completion date.

 

 

 

 

Expected Impact:

 

Upon completion, this project will significantly improve the operations and efficiency of service to Harris County Precinct One Community, through a better equipped and modernized facility. This change order will ensure the interior and exterior requirements are within compliance.

 

Alternative Options:

 

Commissioner court could postpone the change order, which would postpone the completion of the project.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/9/2021

239

Approved - Project Advertisement - Transmittal by the Office of the Purchasing Agent of a project scheduled for advertisement for construction of a new Administration Office and Service Center in Precinct 1 for the Office of the County Engineer (210309).

2/22/2022

243

Approved - Contract Award - Request for approval of an award on the basis of best proposal meeting requirements to Brookstone, LP in the amount of $21,700,000 for construction of a new Administration Office and Service Center in Precinct 1, subject to applicable bonds to be received (210309).

8/8/2023

41

Approved - Change in Contract# 21/0309-1 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $583,758.00, Job No. 21/0309-1, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal 17%.

9/19/2023

55

Approved - Change in Contract# 21/0309-2 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $49,267.00, Job No. 21/0309-2, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal 17%.

10/10/2023

56

Approved - Change in Contract# 21/0309-3 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding an additional amount of $18,085.00, Job No. 21/0309-3, UPIN 20101MF1ET01, Precinct 1.

11/14/2023

40

Approved - Change in Contract# 21/0309-4 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $35,726.00, Job No. 21/0309-4, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%

12/5/2023

43

Approved - Change in Contract# 21/0309-5 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $33,776.00, Job No. 21/0309-5, UPIN 20101MF1ET01, Precinct 1.

12/19/2023

44

Approved - Change in Contract# 21/0309-6 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 163 calendar days, with an addition in the amount of $382,123.00, Job No. 21/0309-6, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 17%.

12/30/2023

77

Approved - Change in Contract# 21/0309-7 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $89,972.00, Job No. 21/0309-7, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%

3/26/2024

54

Approved - Change in Contract# 21/0309-8 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 123 calendar days, with an addition in the amount of $323,326.00, Job No. 21/0309-8, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%

5/7/2024

58

Approved - Change in Contract# 21/0309-9 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $24,042.00, Job No. 21/0309-9, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

5/7/2024

45

Approved - Change in Contract# 21/0309-10 - Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 118 calendar days, with an addition in the amount of $917,863.00, Job No. 21/0309-10, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

6/4/2024

74

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $69,658.00, Job No. 21/0309-11, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%. MWDBE Current Participation: 32%.

6/25/2024

54

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $32,613.00, Job No. 21/0309-12, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

8/6/2024

49

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, adding 74 calendar days, with an addition in the amount of $264,033.00, Job No. 21/0309-13, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

8/27/2024

61

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $102,075.00, Job No. 21/0309-14, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

9/19/2024

48

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $60,329.00, Job No. 21/0309-15, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

11/12/2024

71

Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, with an addition in the amount of $38,003.00, Job No. 21/0309-16, UPIN 20101MF1ET01, Precinct 1, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 32%.

 

Location:

Address (if applicable): 2787 El Camino Street, Houston, TX 77054

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1000 - General Fund

$

$35,206.00

$35,206.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$35,206.00

$35,206.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$35,206.00

$35,206.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 1/9/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Truitt Rounsavall, PE, MBA, PMP, LSSBB, Assistant Director of Capital Project Facilities, Engineering Group

 

 

Attachments (if applicable): County Auditor’s Form 1258B (Job No. 21/0309-17)