File #: 24-5687    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/5/2024 In control: Commissioners Court
On agenda: 9/19/2024 Final action: 9/19/2024
Title: Request for approval of a change in contract with Reytec Construction Resources, Inc., in connection with Oak Glen Place Subdivision Drainage Improvements - 2018, adding six calendar days, with an addition in the amount of $28,639.96, Job No. 23/0028-3, UPIN 19101MF13601, Precinct 2, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 26.07%.

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): UPIN - 19101MF13601 - Job No. 23/0028

Vendor/Entity Legal Name (if applicable): Reytec Construction Resources, Inc.

 

MWDBE Contracted Goal (if applicable): 21%

MWDBE Current Participation (if applicable): 26.07%

Justification for 0% MWDBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Reytec Construction Resources, Inc., in connection with Oak Glen Place Subdivision Drainage Improvements - 2018, adding six calendar days, with an addition in the amount of $28,639.96, Job No. 23/0028-3, UPIN 19101MF13601, Precinct 2, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 26.07%.

end

 

Background and Discussion:

The location of the work is in the Oak Glen Place (East) subdivision in the Halls Bayou Watershed. The proposed improvements include installation of a new storm sewer system, driveways paving, widening, and regrading of existing roadside ditches, and construction of a new detention pond.

 

The Change in contract is needed to reconcile the overrunning items with the underrunning items and adding a new line item to the contract. Below is a summary of changes:

 

                     Added a new line item #146 - swapping asphalt driveways with 6” reinforced concrete driveways and item #151 - replacement of existing concrete walkways for an additional cost in the amount of $325,523.00 and 6 calendar days.

 

                     Quantity Adjustment: The items are adjusted to reconcile overrun and underrun quantities on the project. The increase of quantities removing asphalt driveways, crushed aggregate driveways, filter fabric barrier, (items 4, 18 and 117) for an addition in the amount of $23,304.96.

 

                     The decrease of quantities on underrun line item#20 for a deduction in the amount of $320,188.00

 

                     The above additions and deductions resulted in a net addition to the contract in the amount of $28,639.96 and 6 calendar days.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Oak Glen Place (East) subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

Alignment with Goal(s):

_ Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

X Transportation

X Flooding

_ Environment

_ Governance and Customer Service

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

04/04/2023

23-2090

Award of Construction Contract- Reytec Construction Resources, Inc.

10/31/2023

23-6241

Contract Amendment (23/0028-1) for additional funds and extension to project term

06/04/2024

24-3340

Contract Amendment (23/0028-2) for additional funds and extension to project term

 

Location: Oak Glen Place (East) Drainage Subdivision

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

$28,639.96

$ 28,639.96

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$28,639.96

$ 28,639.96

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Request

$

$28,639.96

$ 28,639.96

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: September 19, 2024

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department

 

Attachments (if applicable): Change in Contract (CIC)