Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): Raba Kistner, Inc.
MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Raba Kistner, Inc. for construction materials testing services for the replacement of pavement terminal anchor sections on bridges of Hardy Toll Road in the amount of $330,000.00 (Precincts 1, 2, and 3, MWBE Contracted Goal: 19.6%).
end
Background and Discussion:
On March 27, 2025, Commissioners Court approved negotiations with Raba Kistner, Inc. for construction materials testing. The construction materials testing services will provide material testing during construction of structural elements that were identified to undergo replacement.
Expected Impact:
Improved roadway conditions and extension of life expectancy for bridges.
Alternative Options:
No other recommended option for this identified need.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
3/27/2025 |
203 |
Request to Negotiate |
Location:
Address (if applicable): N/A
Precinct(s): Precincts 1, 2, & 3
Fiscal and Personnel Summary |
Service Name |
Roadway & Facility Infrastructure Maintenance |
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Revenue - TRA |
$ |
$100,000 |
$100,000 |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Existing Budget |
$ |
$100,000 |
$100,000 |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Sources |
$ |
$100,000 |
$100,000 |
$ |
Grants - Proposed Budget (To be filled out by Grants staff only) |
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: 6/12/2025
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority
Attachments (if applicable): Agreement