Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): 22101MF2F801
Vendor/Entity Legal Name (if applicable): CenterPoint Energy
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with CenterPoint Energy Houston Electric, LLC, in the amount of $49,423 to relocate power poles within Deussen Park, in connection with Deussen Park - Trails, Waterfront, and Parking - 2021, UPIN 22101MF2F801, Precinct 1.
end
Background and Discussion:
The project is to construct waterfront structures, parking lot, boardwalk, trail, lighting and landscape in both Alexander Deussen and Dwight D. Eisenhower Parks. It also includes the construction of a two span, signature pedestrian bridge with parapet panel over West Canal at Aqueduct Road to provide the pedestrian, hike and bike connection between Deussen Park and Eisenhower Park as part of the park trail system. The West Canal pedestrian bridge construction requires CenterPoint Energy to relocate the power poles within Deussen Park for both construction and permanent conditions. These conflict power poles are within the existing utility easement.
Expected Impact:
This action will resolve the conflict condition and provide safe zone during the construction.
Alternative Options:
No action will result in the conflicting condition and unsafe construction environment.
Alignment with Goal(s):
X Justice and Safety
_ Economic Opportunity
_ Housing
X Public Health
X Transportation
_ Flooding
_ Environment
X Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
N/A |
N/A |
N/A |
Location: Alexander Deussen Park
Address (if applicable): N/A
Precinct(s): Precinct 1
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Bonds |
$ |
$49,423.00 |
$49,423.00 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$49,423.00 |
$49,423.00 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$49,423.00 |
$49,423.00 |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: July 15, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): Agreement