Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 22035MF28501
Vendor/Entity Legal Name (if applicable): CenterPoint Energy
MWDBE Contracted Goal (if applicable): n/a
MWDBE Current Participation (if applicable): n/a
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a service outlet location statement for the installation of an electric meter with CenterPoint Energy and authorize the County Auditor to pay monthly bills for 19044 ½ Cypress Rosehill Rd, Cypress, TX 77429 (intersection of Cypress Rose Hill Rd at Juergen Rd) for electrical power serving a traffic signal, Precinct 4.
end
Background and Discussion:
A traffic study was conducted at Cypress Rose Hill Rd at Juergen Rd, which warranted a traffic signal at the intersection. The traffic signal will enhance safety as it relates to the intersection operations. The service outlet location statement is needed to establish electrical service from CenterPoint Energy to power the traffic signal.
Expected Impact:
Approval of the service outlet location statement will allow CenterPoint Energy to establish electrical service to the traffic signal, which is needed to enhance the safety and operation of the intersection of Cypress Rose Hill Rd at Juergen Rd.
Alternative Options:
All Traffic Signals require a power source, which is typically obtained through CenterPoint Energy. Alternative options are to place a generator, which is not reliable, or not install the traffic signal at the intersection. Both options pose a public safety concern and will impact the operation and increase delay of the intersection.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
06/08/2021 |
58 |
ATN |
07/20/2021 |
97 |
Professional Services Agreement |
01/25/2021 |
79 |
SOLS/Utility Agreement |
Location:
Address (if applicable): 19044 ½ Cypress Rosehill Rd, Cypress, TX 77429
Precinct(s): Precinct 4
Fiscal and Personnel Summary |
Service Name |
|
|
SFY 22 |
FY 23 |
Next 3 FYs |
Incremental Expenditures (do NOT write values in thousands or millions) |
Labor Expenditures |
$ |
$ |
$ |
Non-Labor Expenditures |
$2,100.00 |
$700.00 |
$3,600.00 |
Total Incremental Expenditures |
$2,100.00 |
$700.00 |
$3,600.00 |
Funding Sources (do NOT write values in thousands or millions) |
Existing Budget |
1000 - General Fund |
$2,100.00 |
$700.00 |
$3,600.00 |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Current Budget |
$2,100.00 |
$700.00 |
$3,600.00 |
Additional Budget Requested |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
Total Additional Budget Requested |
$ |
$ |
$ |
Total Funding Sources |
$2,100.00 |
$700.00 |
$3,600.00 |
Personnel (Fill out section only if requesting new PCNs) |
Current Position Count for Service |
- |
- |
- |
Additional Positions Requested |
- |
- |
- |
Total Personnel |
- |
- |
- |
Anticipated Court Date: August 2, 2022
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Tina Liu, Traffic Design and Operations Interim Manager, Engineering Department
Attachments (if applicable): SOLS