Legislation Details

File #: 24-3145    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 5/20/2024 In control: Commissioners Court
On agenda: 6/4/2024 Final action: 6/4/2024
Title: Request for approval of a Final Investment Memo for the 1001 Preston - Administration Building - Updates and Renovations project for an additional amount of $12,500,000 for a total of $13,800,000 and for approval of additional commercial paper allocation in the amount of $5,000,000 for a total of $6,300,000.

 

Department: County Engineer

Department Head: Dr. Milton Rahman, PhD., P.E., PMP, CFM, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo

Investment Memo Type: Final Investment Memo

 

Project Name: 1001 Preston - Administration Building - Updates and Renovations

Project ID (if applicable): ADMIN_BLDG_RENO

Vendor Legal Name (if applicable): N/A

 

MWDBE Contracted Goal (if applicable): N/A

MWDBE Current Achievement (if applicable): N/A

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Managing Entity: County Engineer

Incremental Authorization Requested: $12,500,000

Total Estimated Project Cost: $13,800,000

 

Request Summary:

title

Request for approval of a Final Investment Memo for the 1001 Preston - Administration Building - Updates and Renovations project for an additional amount of $12,500,000 for a total of $13,800,000 and for approval of additional commercial paper allocation in the amount of $5,000,000 for a total of $6,300,000.

end

 

Project Description:

On 10/31/2023, Commissioners Court approved Phase 1 of the project, which consisted of professional services for the programming and design of Suite 911, as well as security planning and construction to the 1st floor.

The Office of County Engineer is returning to Commissioners Court for approval of Phase 2 funding for the construction and the renovations to Suite 911 on the 9th floor. Phase 2 of the project also involves the design, upgrades, and renovations needed for Suite 950 on the 9th floor and Suite 450 on the 4th floor.

 

Project Scope:

Phase 1 of the project entailed procuring professional services for the design of Suite 911 situated on the 9th floor, alongside enhancements to security systems on the 1st floor, and ADA improvements throughout.

Phase 2 involves the abatement, demolition, and construction for Suite 911 located on the 9th floor.

The design and construction for Suite 950 and Suite 450 within the building are also included in this phase. Renovations will consist of upgrading mechanical, electrical, and plumbing systems to meet current codes and standards while improving the energy efficiency of the space. Additional upgrades included in the scope of the project are IT/AV upgrades, fire and life safety upgrades, and accessibility upgrades to meet current codes and regulations throughout the space. These upgrades will maximize utilization of the existing spaces while providing a healthier work environment.

Justification:

The project aims to reconfigure and modernize the layout of suites situated on both the 9th and 4th floors to better suit the requirements of Harris County staff. Through this renovation, energy-efficient upgrades will be implemented to optimize operational costs, particularly maintenance and electricity expenses. Upgrades will also provide a healthier working environment to the staff occupying the spaces. Significant security upgrades will be included to ensure the safety of the county staff and visitors to those spaces.

Alternatives and Engagement:

The alternative option is to make no changes or updates to the building. However, maintaining the building in its current state entails higher operational and maintenance expenses, as well as operational losses due to the inefficient and outdated configuration of the spaces prior to modern technology and business practices. Outdated systems will necessitate ongoing repairs and maintenance, which are likely to incur escalating costs over time, especially considering the impact of inflation.

Anticipated Project Expenditures and Timeline:

Scope of Work

Estimated Cost

Estimated Completion

Previous PIM approved 10/31/23 (A&E services for Design of 9th floor, security improvements to 1st floor, ADA Improvements, and Space Planning)

$1,300,000

Q3 FY24

CMT Testing for 9th and 4th floor suites

$30,000

Q3 FY25

9th Floor Renovations Design and Construction

$6,620,000

Q4 FY25

4th Floor Renovations Design and Construction

$3,400,000

Q4 FY25

Temporary Office Space Renovation 

$650,000

Q4 FY24

Contingency

$1,800,000

Q4 FY24

Total - Phase 2 (Current FIM Request)

$12,500,000

 

Project TOTAL

$13,800,000

-

 

 

Alignment with Goal(s):

X Justice and Safety

_ Economic Opportunity

_ Housing

_ Public Health

_ Transportation

_ Flooding

_ Environment

_ Governance and Customer Service

 

Previous Court Action:

Date

Agenda Item #

Action Taken

10/31/2023

23-6201

Request for approval of PIM for $1,300,000

 

Address: 1001 Preston Street, Houston, TX 77002

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

 

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

 

 

 

 

 

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

 

 

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Current Budget

$

$

$

$

Additional Budget Request

 

Commercial Paper

 

$5,000,000

$5,000,000

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$5,000,000

$5,000,000

$

Total Funding Request

$

$5,000,000

$5,000,000

$

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: June 04, 2024

Anticipated Implementation Date (if different from Court date):

Legal funding compliance confirmed by: Paige Abernathy, Assistant District Attorney, 05/23/2024

Department Approval by: Ross Hosket, P.E., CFM, Env SP, Interim Director, Capital Project Facility 

OMB CIP Team Approval by: William McGuinness, Director - Capital Projects & Infrastructure, 05/23/2024

 

 

Commercial Paper Request (For OMB use only):

Receiving Department: County Engineer

Project PeopleSoft ID: ADMIN_BLDG_RENO

CP Series Description: Commercial Paper Series D-2 can be used for (1) construction of public works, (2) the purchase of automobiles, equipment and machinery, including computers, materials and supplies for the operation of the County’s precincts and departments (3) Professional services, including services provided by engineers, architects, attorneys, auditors, financial advisors, and fiscal agents, in connection with the contractual obligations described in (1) and (2).

Commercial Paper is being requested for the 1001 Preston -- Administration Building - Updates and Renovations project and is expected to be repaid within the next three fiscal years either through bonds, budgetary means or pay-as-you-go sources.

 

OMB Financial Management contact: Amy Perez, Deputy Executive Director, Office of Management and Budget