File #: 25-4100    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/23/2025 In control: Commissioners Court
On agenda: 7/10/2025 Final action: 7/10/2025
Title: Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainage Improvements, adding 14 calendar days, with no change in the amount, Job No. 23/0178-4, UPIN 23208MF2TN01, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.
Sponsors: Mony Hossain

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0178, UPIN 23208MF2TN01

Vendor/Entity Legal Name (if applicable): Reliance Construction Services, L.P.

 

MWBE Contracted Goal (if applicable): 24%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainage Improvements, adding 14 calendar days, with no change in the amount, Job No. 23/0178-4, UPIN 23208MF2TN01, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.

end

 

Background and Discussion:

The Beaumont Place Subdivision is located in the Greens Bayou watershed near Highway 90 and Beltway 8. The proposed improvements include roadside ditch regrading, driveway culvert upgrades, expansion of channel along Big Gulch, concrete lined Sulphur Gully channel with reinforced concrete box (RCB) crossing improvements. Improvements also include multiple detention ponds along Big Gulch with an extreme event overflow swale towards the upstream portion of the channel.

 

The change in contract includes the following:

 

                      An additional 14 calendar days are requested due to delays associated with additional culvert, sidewalk, and driveway installations, redesigned storm sewer details along the Phases I and II interface at Flagstaff Ln, redesigned grading along the roadside ditch over existing Magellan and ExxonMobil pipelines, and the installation of an 8x4 RCB. These conflicts, which impacted the proposed installation of storm sewer and excavation of roadside ditches required extended coordination

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Beaumont Place subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

05/16/2023

358 (23-2817)

Transmittal - Advertisement

06/27/2023

258 (23-3607)

Contract Award - Reliance Construction Services, L.P.

12/10/2024

100 (24-7495)

Contract Amendment (23/0178-1) for additional funds

01/23/2025

67 (25-0628)

Contract Amendment (23/0178-2) for additional funds

 

Location: Beaumont Place subdivision, Houston, TX

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 7/10/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC)