Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Termination
Project ID (if applicable): UPIN 19103MF14501
Vendor/Entity Legal Name (if applicable): Costello, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a Mutual Termination Agreement with Costello, Inc. in connection with the Cypress Crossing Mobile Home Park Drainage Improvements - 2018, UPIN 19103MF14501, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
The professional Services contract was originally executed on September 15, 2020 with Costello, Inc. Per court action on February 21, 2023 this project was placed on Table 3 - Additional Potential Reductions.
Expected Impact:
Approving this Termination of Agreement complies with the court action taken on February 21, 2023 for Table 3 - Additional Potential Reductions.
Alternative Options:
No alternative option. Both parties agree to mutually terminate the agreement.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date |
Agenda Item # |
Action Taken |
02/21/2023 |
37 |
Adoption of recommendations 1, 2, and 4 as presented and to add the following: Pause the project identified in Table 3 of Item 37, pending additional partner participation or precinct funding |
10/25/2022 |
63 |
Acceptance of Study Report |
09/15/2020 |
5 |
Contract Award for Professional Engineering Service |
12/17/2019 |
17 |
Authorization to Negotiate |
Location:
Address (if applicable): Cypress Crossing Mobile Home Park
Precinct(s): Precinct 3
Fiscal and Personnel Summary |
Service Name |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
Funding Sources |
|
Existing Budget |
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Current Budget |
$ |
$ |
$ |
$ |
Additional Budget Request (Requires Fiscal Review Request Form) |
|
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Choose an item. |
$ |
$ |
$ |
$ |
Total Additional Budget Request |
$ |
$ |
$ |
$ |
Total Funding Request |
$ |
$ |
$ |
$ |
Personnel (Fill out section only if requesting new PCNs) |
|
Current Position Count for Service |
- |
- |
- |
- |
Additional Positions Request |
- |
- |
- |
- |
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: February 27, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: : Erwin Burden, P.E., CFM, Director of Disaster & Resiliency Division, Harris County Engineering Department
Attachments (if applicable): : Mutual Termination Agreement