Title: Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45 - 2019, adding 6 calendar days, with a deduction in the amount of $580,975.50, Job No. 20/0124-4, UPIN 19101MF19201, Precinct 1.
Attachments: 1. CIC-19101MF19201-UofH Cullen-20-0124-4.final-Texas Materials-P1-12112025.pdf

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 20/0124, UPIN 19101MF19201

Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.

 

MWBE Contracted Goal (if applicable): N/A

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - project was awarded prior to launch of County's M/WBE Program

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45 - 2019, adding 6 calendar days, with a deduction in the amount of $580,975.50, Job No. 20/0124-4, UPIN 19101MF19201, Precinct 1.

end

 

Background and Discussion:

This project is a transportation improvement project for  Transportation Improvements near University of Houston - Cullen Blvd (Seg B) from S. of Wheeler Ave to IH45, which includes the reconstruct of Cullen Boulevard, new underground storm sewer systems, new 12 foot shared-use patch, 1 new signal, signal modification at 6 intersections, installation of landscaping irrigation system and new street lights in Precinct 1.

 

This change in contract includes the final accounting of bid items for a final payment.

 

The substantial completion date for the project will be set for Sept 16, 2024. In accordance with Section 5.3 of the General Conditions, (1) time of the essence, and (2) delay damages will apply past the new substantial completion date.

 

 

Expected Impact:

Changes will allow for the project to be closed out in accordance with contracted amounts and agreed upon changes.

 

Alternative Options:

None.

 

County Strategic Plan Goal:  N/A

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

 

Date

Agenda Item #

Action Taken

07/14/2020

19.d.9.c

Contract Award

05/11/2021

24 (21-1946)

Contract Amendment #1 for additional funds and extension of project term

08/23/2022

45 (22-5005)

Contract Amendment #2 for additional funds and extension of project term

07/15/2024

62 (24-4099)

Contract Amendment #3 for additional funds and extension of project term

 

Location:

Address (if applicable): Cullen Boulevard, Houston, Texas 77004

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1070 - Mobility Fund 3109

$

-$580,975.50

-$580,975.50

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$580,975.50

-$580,975.50

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$580,975.50

-$580,975.50

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 12/11/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B