File #: 25-3365    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 5/23/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval to execute an agreement with Infrastructure Engineering Inc., in the amount of $1,318,123.00 for Professional Engineering Services to provide roadway, storm sewer and sidewalk improvements along Hafer Road from FM 1960 to Skywood Drive, UPIN 25101MF3N301, Precinct 1, MWBE Contracted Goal: 19.6%.
Attachments: 1. 25-3365-Award-25101MF3N301-Infrastructure Engineering-

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): UPIN 25101MF3N301

Vendor/Entity Legal Name (if applicable): Infrastructure Engineering, Inc.

 

MWBE Contracted Goal (if applicable): 19.6%

MWBE Current Participation (if applicable): 0%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval to execute an agreement with Infrastructure Engineering Inc., in the amount of $1,318,123.00 for Professional Engineering Services to provide roadway, storm sewer and sidewalk improvements along Hafer Road from FM 1960 to Skywood Drive, UPIN 25101MF3N301, Precinct 1, MWBE Contracted Goal: 19.6%.

end

 

Background and Discussion:

The project is to design the reconstruction of Hafer Road, approximately one mile, from FM 1960 to Skywood Drive.  The reconstruction includes a new concrete pavement with storm sewer and detention basin, sidewalk, and a traffic signal.

 

Expected Impact:

The proposed improvement will provide a safe condition for the vehicular and pedestrian traffic with better drainage system requiring less maintenance.

 

Alternative Options:

No Alternative options. If not approved, project will be delayed or could get canceled.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  G1: Expand pedestrian and cyclist infrastructure on County-managed roads,

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan:

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

N/A

N/A

 N/A

 

Location: Hafer Road from FM 1960 to Jester Boulevard, Walters Road near Claughton Middle School

Address (if applicable):  N/A

Precinct(s): Precinct 1

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other  3002

$

$1,318,123.00

$1,318,123.00

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$1,318,123.00

$1,318,123.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$1,318,123.00

$1,318,123.00

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 6/12/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services, Office of the County Engineer.

 