Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Negotiation
Project ID (if applicable): UPIN - 19101MF17F01
Vendor/Entity Legal Name (if applicable): All-Terra Engineering
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to negotiate with All-Terra Engineering for professional services regarding construction materials testing for Parkway (Mobile Homes) Subdivision Drainage Improvements - 2018, UPIN 19101MF17F01, Precinct 1.
end
Background and Discussion:
The Parkway (Mobile Homes) Subdivision is located in Precinct 1, northeast Harris County, north of the
intersection of Park Trail Drive and Tidwell Road. The existing drainage system consists of concrete curb and gutter, and surface flow to a main trunkline drainage culvert that runs south and ultimately outfalls into HCFCD maintained ditch P122-00-00. The scope of project includes construction of underground drainage improvements, stormwater detention basin, and concrete pavement. All-Terra Engineering will provide construction materials testing services to support the project in construction.
Expected Impact:
This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials to ensure the material’s compliance with Harris County Engineering Department’s adopted standards and specifications as required by state law.
Alternative Options:
Construction materials testing is required by state law.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
|
|
|
Location: Parkway (Mobile Homes) Subdivision
Address (if applicable): N/A
Precinct(s): Precinct 1
|
Fiscal and Personnel Summary |
|
Service Name |
Professional Services - CMT |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: October 29, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director of Capital Project Infrastructure, Harris County Engineering Department
Attachments (if applicable): N/A