Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Treviño, P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Proposals/Bids
Project ID (if applicable): Job No. 25/0279
Vendor/Entity Legal Name (if applicable): Durwood Greene Construction Co.
MWBE Contracted Goal (if applicable): 12.11%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a construction contract award to Durwood Greene Construction Co., for Pavement Surface Repairs at SH 249 Tomball Tollway in the amount of $7,363,337.87 (Precincts 3 and 4; MWBE Contracted Goal: 12.11%).
end
Background and Discussion:
The October 16, 2025 Commissioners Court approved the advertisement for low bid construction contract. The construction contractor will provide services for the pavement surface replacement of SH 249 Tomball Tollway which is due for maintenance in the section that was installed in 2015. The existing surface is an asphalt Permeable Friction Course (PFC) which currently has a 5-8 year-life cycle.
Expected Impact:
Project will provide improved roadway conditions. Funding for this request will come from the Toll Road Authority.
Alternative Options:
No other recommended solutions for this identified need.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
1/9/2025 |
154 |
Award Design |
|
10/16/2025 |
154 |
Request to Advertise Construction |
Location:
Address (if applicable): N/A
Precinct(s): Precincts 3 & 4
|
Fiscal and Personnel Summary |
|
Service Name |
Roadway & Facility Infrastructure Maintenance |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Revenue - TRA |
$ |
$3,000,000 |
$3,000,000 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$3,000,000 |
$3,000,000 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$3,000,000 |
$3,000,000 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 1/8/2026
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Nicole Stuttz, Chief of Staff, Harris County Toll Road Authority
Attachments (if applicable): N/A