Legislation Details

File #: 26-2231    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/31/2026 In control: Commissioners Court
On agenda: 4/16/2026 Final action: 4/16/2026
Title: Request for approval of a change in contract with Environmental Allies, Inc. in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, adding 151 calendar days, with no change in the amount, Job No. 24/0084-4, UPIN 22102MF2G801, Precinct 2, MWBE Contracted Goal: 28.35%, MWBE Current Participation: 24.48%.
Attachments: 1. 26-2231-CIC-22102MF2G801-Vickery Street-24-0084-4-Environmental Allies-P2-04162026

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0084, UPIN 22102MF2G801

Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.

 

MWBE Contracted Goal (if applicable): 28.35%

MWBE Current Participation (if applicable): 24.48%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Environmental Allies, Inc. in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, adding 151 calendar days, with no change in the amount, Job No. 24/0084-4, UPIN 22102MF2G801, Precinct 2, MWBE Contracted Goal: 28.35%, MWBE Current Participation: 24.48%.

end

 

Background and Discussion:

The project consists of improvements to the intersection of Vickery Street at Lauder Road, including road widening, turning lanes, full-width concrete replacement, sidewalks, bus pads and a traffic signal

 

Added 151 days to the contract due to delays associated with procurement and installation of the traffic signal controller box.  The controller box experienced manufacturers lead time delays and was shipped on June 30, 2025, and delivered on July 2, 2025.  Installation was further delayed due to a required meter address change, which was completed on September 2, 2025.  Signal installation, inspection, and activation were completed on October 16, 2025.  This change will add 151 additional days.

 

Expected Impact:

Increase the total number of days of the contract.

 

 

Alternative Options:

No action will result in substandard construction.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

05/07/2024

203 (24-2763)

Contract Award

01/23/2025

59 (25-0586)

Contract Amendment #1 for additional funds and extension of project term

05/22/2025

75 (25-3204)

Contract Amendment #2 for additional funds and extension of project term

10/16/2025

32 (25-6160)

Contract Amendment #3 for additional funds

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$0.00

$0.00

$0.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 4/16/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B