Title: Request for approval of a change in contract with Millis Equipment, LLC, in connection with Hufsmith-Kohrville Road 2, adding 35 calendar days, with an addition in the amount of $6,236.89, Job No. 23/0308-4, UPIN 15104M23NP02, Precinct 3, MWBE Contracted Goal: 28.50%, MWBE Current Participation: 33.60%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0308, UPIN 15104M23NP02

Vendor/Entity Legal Name (if applicable): Millis Equipment, LLC

 

MWBE Contracted Goal (if applicable): 28.50%

MWBE Current Participation (if applicable): 33.60%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Millis Equipment, LLC, in connection with Hufsmith-Kohrville Road 2, adding 35 calendar days, with an addition in the amount of $6,236.89, Job No. 23/0308-4, UPIN 15104M23NP02, Precinct 3, MWBE Contracted Goal: 28.50%, MWBE Current Participation: 33.60%.

end

 

Background and Discussion:

Project included the reconstruction of Hufsmith-Kohrville Rd from Hollow Glen Lane to 500' North of Ezekiel from 2 lane asphalt road to 4 lane concrete curb and gutter boulevard with 32' raised median with traffic signals at Lacey Road and Ezekiel Road.  There are two outfalls within the limits of the project, North Pointe Boulevard and Champion Wood Drive detention ponds.

 

To mitigate conflicts and prioritize critical path, it was necessary to offset the waterline, and monuments were removed to ensure proper intersection sight distance.  Unforeseen site conditions and design adjustments led to quantity changes, resulting in necessary overruns and underruns.  Additionally, the reconstruction of Ezekiel Road-added as a new scope not included in the original contract-is being addressed through this contract modification to fairly compensate the contractor for the additional work.

 

The change in contract includes the following:

New Items:

 

•                     WATER LINE OFFSET AT STATION 78+00                                                                                    1 LS = $12,755.34

•                     REMOVAL OF MONUMENTS                                                                                                                               2 EA = $7,297.28

•                     REMOVAL OF TREES                                                                                                                                                      7 EA = 14,594.58

•                     RECONSTRUCTION OF EZEKIEL INTERSECTION                                                                  1 LS = $261,560.09

 

Existing items overrun:

ROADWAY EXCAVATION INCLUDING 3" TOPSOIL                                                                                    311.78                     CY = $7,326.83

MILLING EXISTING PAVEMENT (UP TO 3")                                                                                                         36.22 SY = $152.12

REMOVING OLD STRUCTURES - MANHOLES (ALL DEPTHS)                                                               2 EA = $1,834.00

REMOVING OLD STRUCTURES - SAFETY END TREATMENTS                                                               1 EA = $1,380.00

CONSTRUCTION SAFETY FENCE                                                                                                                              1,600 LF = $7,360.00

HMAC TACK COAT                                                                                                                                                                        1,885 GL = $10,367.50

HOT MIX - 2" HOT LAID ASPHALTIC CONCRETE                                                                                    381.86                     TN= $68,734.80

CONCRETE PAVEMENT (10")                                                                                                                                                   1,813.32 SY = $149,598.90

CONCRETE DRIVEWAY (10") (HIGH STRENGTH)                                                                                    538.56                     SY = $49,278.24

CEMENT STABILIZED SAND (6" THICK FOR HIGH STRENGTH CONCRETE)                     1,698.01 SY = $28,017.17

REINFORCED CONCRETE RETAINING WALL                                                                                                         13.6 CY = $21,896.00

JUNCTION BOX FOR 36" RCP                                                                                                                                 7 EA = $40,390.00

TYPE A INLET WITH CONCRETE APRON                                                                                                         1 EA = $4,250.00

PRECAST RCB (4' X 4')                                                                                                                                                                        14.32 = $6,844.96

PRECAST RCB (5' X 4')                                                                                                                                                                        5.32 LF                      = $3,032.40

MANHOLE WITH RESTRICTOR PLATE                                                                                                                              1 EA = $9,960.00

12-INCH PVC WATER LINE BY OPEN CUT                                                                                                         56 LF = $8,288.00

12-INCH PVC WATER LINE WITH 24" CASING (TRENCHLESS)                                                               8 LF = $2,488.00

WORK ZONE TYPE 2-A-A REFLECTORIZED PAVEMENT MARKER                                           1,130 EA = $4,746.00

WORK ZONE TRAFFIC BUTTON, YELLOW, NON-REFLECTORIZED                                           2,504 EA = $10,516.80

TRAFFIC CONTROL PLAN                                                                                                                                                    2.57 MO = $13,569.60

TEMPORARY PIPE UNDER DRIVEWAY                                                                                                          158.8 LF = $17,944.40

FURNISH AND INSTALL 4" SOLID YELLOW                                                                                                         981 LF = $882.90

FURNISH AND INSTALL 12" SOLID WHITE                                                                                                         108 LF = $367.20

FURNISH AND INSTALL 4" DIA. TRAFFIC BUTTON, YELLOW                                                               242 EA = $1,210.00

FURNISH AND INSTALL TYPE 2-A-A                                                                                                                               351 EA = $2,106.00

FURNISH AND INSTALL 1" SCHEDULE 40 PVC CONDUIT                                                               88 LF = $2,332.00

FURNISH AND INSTALL 4" SCHEDULE 40 PVC CONDUIT                                                               65 LF = $2,242.50

FURNISH AND INSTALL 4" X 15' SCH. 80, SPUN ALUMINUM POLE                                          1 EA = $2,990.00

FURNISH AND INSTALL LOOP DETECTORS IN CONCRETE PAVEMENT                     178 LF = $2,047.00

FURNISH AND INSTALL #4 AWG, XHHW (STRANDED) WIRE                                                               743 LF = $3,380.65

FURNISH AND INSTALL 2/C #14 AWG (IMSA 20-1) (STRANDED) CABLE                     85 LF = $161.50

FURNISH AND INSTALL 2/C #14 AWG (IMSA 50-2) (STRANDED) CABLE                     2865 LF = $8,165.25

FURNISH AND INSTALL 4/C #14 AWG (IMSA 20-1) (STRANDED)CABLE                     680 LF = $1,530.00

FURNISH AND INSTALL 7/C #14 AWG (IMSA 20-1) (STRANDED) CABLE                     575 LF = $2,300.00

BENCHES FOR SHARED USE PATH AT NORTH POND                                                                                    3 EA = $15,000.00

THERMOPLASTIC PIPE (PP) (18")                                                                                                                              54 LF = $4,806.00

THERMOPLASTIC PIPE (PP) (24")                                                                                                                              9 LF = $918.00

Elim Exist Pav Mrk & Mrks 4"                                                                                                                                                   4,487 LF = $3,858.82

Elim Exist Pav Mrk & Mrks 24"                                                                                                                              128 LF = $309.76

 

Reduction of existing items:

REMOVING OLD CONCRETE (PAVEMENT)                                                                                                         2,980 SY = $25,330.00

REMOVING OLD CONCRETE (CURB)                                                                                                                              1,200 LF = $2,400.00

REMOVE AND DISPOSE OF EXISTING CONCRETE/METAL PIPE                                           450 LF = $9,000.00

REMOVING OLD STRUCTURES - INLETS (ALL DEPTHS)                                                               1 EA = $917.00

HMAC BASE COURSE (8" BLACK BASE)                                                                                                         200 TN = $31,400.00

PRIME COAT FOR BASE COURSE                                                                                                                              420 GL = $1,260.00

CONCRETE PAVEMENT (10") (HIGH STRENGTH)                                                                                    1,850 SY = $166,500.00

REINFORCED CONCRETE CURB (DOWELED)                                                                                                         750 LF = $6,562.50

REINFORCED CONCRETE SIDEWALKS (4-1/2")                                                                                    180 SY = $11,160.00

TRENCH SAFETY SYSTEM (FROM 5 TO 10 FEET)                                                                                    5,268 LF = $12,643.20

REINFORCED CONCRETE PIPE, C76, CLASS III, (24")                                                                                    92 LF = $12,052.00

SET (TYPE II) (24") (RCP) (6:1) (P)                                                                                                                              2 EA = $4,840.00

PRECAST 72" CONCRETE STANDARD MANHOLE                                                                                    10 EA = $73,100.00

TYPE BB INLET                                                                                                                                                                                             1 EA = $5,420.00

PRECAST RCB (6' X 4')                                                                                                                                                                         8 LF = $5,864.00

12-INCH WET CONNECTION                                                                                                                                                   2 EA = $2,060.00

TEMPORARY RESIDENTIAL DRIVEWAYS                                                                                                          11 EA = $12,870.00

TEMPORARY COMMERCIAL DRIVEWAYS                                                                                                          2 EA = $5,980.00

CONSTRUCTING DETOURS (8" BLACK BASE)                                                                                                         2,500 SY = $213,750.00

LOW PROFILE CONCRETE BARRIER (FURNISH AND INSTALL)                                                               580 LF = $38,280.00

LOW PROFILE CONCRETE BARRIER (RELOCATE)                                                                                    5,040 LF = $44,100.00

LOW PROFILE CONCRETE BARRIER (REMOVE)                                                                                    460 LF = $5,750.00

OFF-DUTY UNIFORMED PEACE OFFICE                                                                                                          750 HR = $43,875.00

BORROW (MIN. BID $12/CY)                                                                                                                                                   3,600 CY = $68,400.00

THERMOPLASTIC PIPE (PP) (36")                                                                                                                              6 LF = $990.00

THERMOPLASTIC PIPE (PP) (42")                                                                                                                              35 LF = $8,050.00

 

Expected Impact:

 This change will allow the Contractor to be properly compensated for the additional work.

 

Alternative Options:

Conduct thorough pre-construction assessments and detailed utility mapping to identify and mitigate potential conflicts early.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: F: Ensure safety and security for all using the county’s transportation network in alignment with the County’s Vision Zero plan.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

11/14/2023

204 (23-6678)

Contract Award

06/25/2024

56 (24-3584)

Contract Amendment #1 for additional funds

09/19/2024

51 (24-5681)

Contract Amendment #2 for additional funds and extension of project term

02/06/2025

83 (25-0840)

Contract Amendment #3 for additional funds and extension of project term

 

Location:

Address (if applicable): Hufsmith-Kohrville Rd from Hollow Glen Lane to 500' North of Ezekiel

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 3002, 3109

$

$6,236.89

$6,236.89

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$6,236.89

$6,236.89

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$6,236.89

$6,236.89

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 10/16/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or ARPA related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B