Title: Request for approval of an award on the basis of low bid meeting specifications to Times Construction, Inc. in the amount of $4,715,210 for construction of hike and bike trail along Faulkey Gully for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (250300), MWBE Contracted Goal: 25.92%.

Primary Department: Purchasing

Primary Department Head/Elected Official: Kimberly J. Williams, JD

 

Secondary Department: Commissioner, Precinct 3

Secondary Department Head/Elected Official: Tom Ramsey

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

 

Project ID (if applicable): 250300

Vendor/Entity Legal Name (if applicable): Times Construction, Inc.

 

MWBE Contracted Goal (if applicable): 25.92%

MWBE Current Participation (if applicable): N/A

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable):

Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

 

Request Summary (Agenda Caption):

title

Request for approval of an award on the basis of low bid meeting specifications to Times Construction, Inc. in the amount of $4,715,210 for construction of hike and bike trail along Faulkey Gully for Precinct 3, and for the County Clerk to execute any applicable bonds to be received (250300), MWBE Contracted Goal: 25.92%.

end

 

Background and Discussion:

OCE was notified by the Purchasing Department that the low bidder, TWL Construction, withdrew their bid submission.  Based on the bid results, the recommendation of OCE and the design consultant, IDS Engineering Group, Inc., it is recommended that the lowest responsive bidder, Times Construction, Inc., be awarded the contract.

 

Expected Impact:

Awarding the contract will allow the recommended bidder to proceed with the constructing the 10-foot-wide asphalt trail, 12-foot-wide concrete pedestrian undercrossing and the pedestrian bridge along Faulkey Gully. 

 

Alternative Options:

The alternative is not to award the contract.  If no action is taken, the hike and bike trail, pedestrian undercrossing and the pedestrian bridge along Faulkey Gully will not be constructed.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  F1: Strengthen the County’s commitment to Vision Zero principles and goals.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

10/16/2025

499

Transmittal by Purchasing of a project scheduled for advertisement

 

Location:

Address (if applicable): Hike and Bike Trail - Faulkey Gully - K142-00-00

Precinct(s): Precinct 3

 

Fiscal and Personnel Summary

Service Name

Construction

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other - 3269 (Joint Participation Funds - Faulkey Gully MUD)

$

$1,300,000.00

$1,300,000.00

$

Other - 3269 (2022 Park Bonds)

$

$3,415,210.00

$3,415,210.00

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$4,715,210.00

$4,715,210.00

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$4,715,210.00

$4,715,210.00

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 1/8/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services,

Office of the County Engineer; Maria Heinzmann, Senior Buyer, Harris County Purchasing                     

 

Attachments (if applicable): Letter