Legislation Details

File #: 25-7125    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/29/2025 In control: Commissioners Court
On agenda: 11/13/2025 Final action: 11/13/2025
Title: Request for approval of a change in contract with Reliance Construction Services, LP, in connection with Water Distribution System - Parkwood Estates Ph 4 Olana Dr - 2022, adding 120 calendar days, with an addition in the amount of $213,904.80, Job No 24/0101-2, UPIN 22289MF29P01, Precinct 2, MWBE Contracted Goal: 23.13%, MWBE Current Participation: 100%.
Attachments: 1. 25-7125-CIC-22289MF29P01-Parkwood Estates-24-0101-1-Reliance Const-P2-11132025

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 24/0101, UPIN 22289MF29P01

Vendor/Entity Legal Name (if applicable): Reliance Construction Services, LP

 

MWBE Contracted Goal (if applicable): 23.13%

MWBE Current Participation (if applicable): 100%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Reliance Construction Services, LP, in connection with Water Distribution System - Parkwood Estates Ph 4 Olana Dr - 2022, adding 120 calendar days, with an addition in the amount of $213,904.80, Job No 24/0101-2, UPIN 22289MF29P01, Precinct 2, MWBE Contracted Goal: 23.13%, MWBE Current Participation: 100%.

... end

 

Background and Discussion:

The project consists of installing a water distribution system to serve Olana Drive. in Precinct 2 of Harris County. The water distribution system includes the installation of waterline along Olana Drive, water service connections to existing residences and the decommissioning of existing wells.  Over all 44 Connection Expected is completed

This change in contract includes:

 

PCO#2: During the final stage of the project, additional applicants requested water service connections beyond the original project scope.  Following discussions with Precinct 2 and Harris County Housing and Community Development, it was determined that approximately 50 additional connections were requested by property owners.  Harris County Housing and Community Development have already approved the required funding and time extension on their end.

 

To accommodate this expansion, additional funding in the amount of $213,904.80 and a 120-day contract time extension are being requested.  These adjustments are not due to contractor shortcomings but are necessary to provide clean and reliable water service to the additional applicants under this project.

 

Expected Impact:

This action allows for the completion of required service connections and to ensure full compliance with all applicable regulations

 

Alternative Options:

Continue with the original plan.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: N/A

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  N/A

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

06/04/2024

372 (24-3172)

Contract Award

08/26/2025

35 (25-5132)

Contract Amendment #1 for additional funds and extension of project term

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Other 2601

$

$213,904.80

$213,904.80

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$213,904.80

$213,904.80

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$213,904.80

$213,904.80

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 11/13/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B