File #: 24-0434    Version: 1 Name:
Type: Public Necessity Status: Passed
File created: 1/18/2024 In control: Commissioners Court
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Request by the Office of the County Engineer for approval of a certain project, decreeing the project to be a public necessity and convenience, directing the Harris County Real Property Division to acquire, for one (1) fee simple tract for the public project known as Sanitary Sewer System Construction - Westfield Estates - 2023, for the purpose of construction of Westfield Estates wastewater system, UPIN 23208MF2XZ01, Precinct 2.
Sponsors: Mony Hossain
Attachments: 1. 24-0434-Public Necessity - UPIN 23208MF2XZ01- Sanitary Sewer System Construction - Westfield Estates -

Department: County Engineer

Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

 

Project ID (if applicable): 23208MF2XZ01

Vendor/Entity Legal Name (if applicable):  Any applicable landowner and/or property interest holder

 

MWDBE Contracted Goal (if applicable):  Not applicable.

MWDBE Current Participation (if applicable):  Not applicable

Justification for 0% MWDBE Participation Goal:  N/A - Goal not applicable to request

 

Request Summary (Agenda Caption):

title

Request by the Office of the County Engineer for approval of a certain project, decreeing the project to be a public necessity and convenience, directing the Harris County Real Property Division to acquire, for one (1) fee simple tract for the public project known as Sanitary Sewer System Construction - Westfield Estates - 2023, for the purpose of construction of Westfield Estates wastewater system, UPIN 23208MF2XZ01, Precinct 2.

end

Background and Discussion:

Harris County requires the acquisition of the property to complete an American Rescue Plan Act grant funded wastewater infrastructure project for the Westfield Estates subdivision in Precinct 2. Westfield Estates currently relies primarily on outdated and failing septic systems for wastewater services. The proposed project consists of approximately 33,000 linear feet of sanitary sewer lines, 3,600 linear feet of sanitary force mains, a proposed lift station, and a possible 750 wastewater service connections. To construct a lift station for the new collection system, Harris County must acquire a suitable property within the subdivision. After analyzing the project area, it was determined the preferred location for the lift station site is at 2302 Chamberlain Street, Houston, TX 77093.

 

Expected Impact:

The proposed wastewater improvements would significantly improve environmental health and safety within the Westfield Estates subdivision, while increasing overall quality of life. Access to wastewater services has a potential to increase developments within the area.

 

Alternative Options:

A different property would need to be selected for the proposed lift station. This could increase construction and design costs and put the project at risk of not meeting the American Rescue Plan grant funding deadlines.

 

 

 

Alignment with Goal(s):

X Justice and Safety

_ Economic Opportunity

_ Housing

X Public Health

_ Transportation

_Flooding

X Environment

_ Governance and Customer Service

 

Prior Court Action (if any): None

Date

Agenda Item #

Action Taken

 

 

 

 

Location:

Address (if applicable): 2302 Chamberlain St., Houston, TX 77093

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

 

 

FY 24

FY 25

Next 3 FYs

Incremental Expenditures (do NOT write values in thousands or millions)

Labor Expenditures

$

$

$

Non-Labor Expenditures

$

$

$

Total Incremental Expenditures

$

$

$

Funding Sources (do NOT write values in thousands or millions)

Existing Budget

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Current Budget

$

$

$

Additional Budget Requested

Choose an item.

$

$

$

Choose an item.

$

$

$

Choose an item.

$

$

$

Total Additional Budget Requested

$

$

$

Total Funding Sources

$

$

$

Personnel (Fill out section only if requesting new PCNs)

Current Position Count for Service

-

-

-

Additional Positions Requested

-

-

-

Total Personnel

-

-

-

 

Anticipated Court Date:  January 30, 2024

Anticipated Implementation Date (if different from Court date):

Emergency/Disaster Recovery Note: COVID-19 related item

Contact(s) name, title, department:  Trevor Smith, Assistant Interim Director, Real Property Division

Attachments (if applicable): Findings and Declarations; Survey Descriptions and Maps