Legislation Details

File #: 25-1247    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 2/14/2025 In control: Commissioners Court
On agenda: 2/27/2025 Final action: 2/27/2025
Title: Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with final construction of Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding 32 calendar days, with a deduction in the amount of $298,894.16, Job No. 23/0074-6, UPIN 19104MF13401, Precinct 2, MWBE Contracted Goal: 27.00%, MWBE Current Participation: 10.35%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 23/0074, UPIN 19104MF13401

Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC

 

MWBE Contracted Goal (if applicable): 27.00%

MWBE Current Participation (if applicable): 10.35%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with final construction of Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding 32 calendar days, with a deduction in the amount of $298,894.16, Job No. 23/0074-6, UPIN 19104MF13401, Precinct 2, MWBE Contracted Goal: 27.00%, MWBE Current Participation: 10.35%.

end

 

Background and Discussion:

The location of the work is in the Fallbrook, Ridgepoint, and Westpoint Subdivisions in the Halls Bayou Watershed. The proposed improvements include installation of a new storm sewer system, roadway paving, channel restoration and desilting.

 

The change in contract includes the following:

 

Quantity Adjustment: The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

 

• The increase of quantities on overrun line-item numbers 4, 6, 27, 47, 61, 64, 69, and 80 for an addition in the

amount of $10,304.10.

• The decrease of quantities on underrun line item numbers 3, 7, 8, 10, 13, 14, 15, 16, 17, 18, 19, 28, 50, 51, 52, 54, 55, 56, 57, 65, 66, 67, 68, 70, 72, 75, 76, 77, 78, 79, 81, 82, 83, 84, 86, 87, 88, 89, 93, 98, 99, and 100 for a deduction in the amount of $309,198.26.

 

• Added 32 calendar to the project time due to a waterline conflict encountered along West Road and due to dewatering the water entering the work zone from outside the project limits.

 

Expected Impact:

This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation
of structural flood damage to homes in the
Fallbrook, Ridgepoint and Westpoint subdivision.

 

Alternative Options:

The County could elect to fund the requested task or choose to reject it.  However, if not approved, the contractor will not be able to complete the scope of work.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H6: Expand neighborhood drainage programs.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

03/14/2023

371 (23-1455)

Transmittal - Advertisement

05/16/2023

266 (23-2912)

Award of Construction Contract- Specialty Construction TX, LLC

04/23/2024

66 (24-2186)

Contract Amendment (23/0074-1) for additional funds and extension of project term

06/04/2024

80 (24-3295)

Contract Amendment (23/0074-2) for additional funds and extension of project term

07/15/2024

68 (24-4056)

Contract Amendment (23/0074-3) for extension of project term

11/12/2024

70 (24-7214)

Contract Amendment (23/0074-4) for additional funds and extension of project term

12/10/2024

102 (24-7496)

Contract Amendment (23/0074-5) for extension of project term

01/23/2025

200 (25-0627)

Transmittal - Substantial Completion- Specialty Construction TX, LLC

 

Location: Fallbrook, Ridgepoint and Westpoint Subdivisions, Fallbrook, Texas

Address (if applicable): N/A

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

1080 - Infrastructure Fund

$

-$298,894.16

-$298,894.16

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

-$298,894.16

-$298,894.16

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

-$298,894.16

-$298,894.16

$

Grants - Proposed Budget (To be filled out by Grants staff only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new PCNs)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

Anticipated Court Date: 2/27/2025

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, P.E., CFM, Chief of Engineering and Architectural Services,

Office of the County Engineer

 

Attachments (if applicable): Change in Contract (CIC) - FINAL