Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): - Job No. 25/0422, UPIN 26103MF3ZQ01
Vendor/Entity Legal Name (if applicable): MC2 Civil, LLC
MWBE Contracted Goal (if applicable): 13.99%
MWBE Current Participation (if applicable): 45.85%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Runneburg Estates Roadway Reconstruction - 2025, with a deduction in the amount of $95,414.10, Job No. 25/0422-1, UPIN 26103MF3ZQ01, Precinct 3, MWBE Contracted Goal: 13.99%, MWBE Current Participation: 45.85%.
end
Background and Discussion:
This project is for roadway reconstruction for the following roads - Alpha Lane, Elton Drive, and Rownita. Reconstruction consists of but not limited to necessary base repairs, milling, and roadway reconstruction as noted in the plans.
This change in Contract includes: The final adjustment (reconciliation of actual quantities used in construction against the bid quantities). -$95,414.10.
Expected Impact:
The expected impact is to credit unused funds of -$95,414.10.
Alternative Options:
None at this time.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
03/19/2026 |
270 (26-1905) |
Contract Award |
Location:
Address (if applicable):
Precinct(s): Precinct 3
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources: |
|
|
Existing Budget |
|
|
|
|
|
Other 2601 |
$ |
-$95,414.10 |
-$95,414.10 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
-$95,414.10 |
-$95,414.10 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$-$95,414.10 |
$-$95,414.10 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date: 11/12/2026
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer
Attachments (if applicable): County Auditor’s Form 1258B