Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0408, UPIN 19102MF15W01
Vendor/Entity Legal Name (if applicable): Precise Services Inc.
MWBE Contracted Goal (if applicable): 22.81%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services Inc., in connection with final construction of Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, with an addition in the amount of $198,593.10, Job No. 24/0408-2, Mobility Fund, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 22.81%, MWBE Current Participation: 100%.
end
Background and Discussion:
This project entails the construction of storm sewer drainage to convey drainage in the Cedar Bayou Park East
and West Subdivision from Sjolander Road to Bayou Boulevard.
The change in contract includes the following:
The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.
• The increase of quantities on overrun line items 02, 03, 04, 12, 68, 76, 83, and 88 for an addition in the amount of $292,888.10.
• The decrease of quantities on underrun line items 31, 41, 84, 93, 100, and 106 for a deduction in the amount of $94,295.00.
The above and additions and deductions result in an addition in the amount of $198,593.10 and zero (0) days.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in Cedar Bayou Park subdivision.
Alternative Options:
The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to receive payment for work performed to complete the scope of work.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H6: Expand neighborhood drainage programs.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to the Strategic Plan: N/A
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
04/04/2023 |
228 (23-1874) |
Contract Award - Serco Construction Group, Ltd. |
|
04/23/2024 |
70 (24-2218) |
Contract Amendment (23/0042-1) for additional funds and extension of project term |
|
04/23/2024 |
379 (24-2461) |
Contract Termination - Serco Construction Group, Ltd. |
|
08/27/2024 |
65 (24-5080) |
Contract Amendment (23/0042-2) for additional funds |
|
08/27/2024 |
55 (24-5071) |
Contract Amendment (23/0042-3) for additional funds |
|
12/10/2024 |
524 (24-7523) |
Transmittal - Advertisement |
|
01/23/2025 |
157 (25-0443) |
Contract Award - Precise Services, Inc. |
|
06/12/2025 |
58 (25-3360) |
Contract Amendment (23/0042-4) for a deduction in funds - Final with Serco Construction Group, Ltd. |
|
03/19/2026 |
59 (26-1637) |
Contract Amendment (24/0408-1) for additional funds and extension of project term - Infrastructure Fund |
|
06/11/2026 |
378 (26-3628) |
Transmittal - Substantial Completion |
|
06/25/2026 |
16 (26-3929) |
Contract Amendment (24/0408-2) for additional funds and extension of project term - Infrastructure Fund |
|
06/25/2026 |
17 (26-3944) |
Contract Amendment (24/0408-1) for additional funds and extension of project term - Mobility Fund |
Location: Cedar Bayou Park subdivision
Address (if applicable): N/A
Precinct(s): Precinct 2
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
1070 - Mobility Fund |
$ |
$198,593.10 |
$198,593.10 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Existing Budget |
$ |
$198,593.10 |
$198,593.10 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Sources |
$ |
$198,593.10 |
$198,593.10 |
$ |
|
Grants - Proposed Budget (For Grants Items only) |
|
|
Labor |
Non-Labor |
Total |
No. of Grant Years |
|
Local Match Source - Existing Budget: Choose an item. |
$ |
$ |
$ |
|
|
Local Match Source - Additional Budget Request: Choose an item. |
$ |
$ |
$ |
|
|
Grant Funds Applied for/Awarded (Total) |
$ |
$ |
$ |
|
|
Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
|
County Attorney’s Office Legal Review (for Harris County Code Items only) |
|
CAO Reviewer Name and Title |
|
CAO Review Completion Date |
Click or tap to enter a date. |
Anticipated Court Date 09/17/2026
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer
Attachments (if applicable): Change in Contract (CIC)