Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Asset Management
Project ID (if applicable): 23090MF2PD01
Vendor/Entity Legal Name (if applicable): Harris County Flood Control District
MWDBE Contracted Goal (if applicable): Not Applicable
MWDBE Current Participation (if applicable): Not Applicable
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of an Order authorizing and directing Harris County to abandon its interest in a 60’ foot right of way known as Nanes Drive and Tigris Lane for the purpose of constructing a stormwater detention basin and development of a flood reduction facility from Westador Stormwater Detention Basin - K500-27-00-E001 project, tract K141-00-00-01-010.0, UPIN 23090MF2PD01, Precinct 1.
end
Background and Discussion:
The project site consists of Approximately 38 acres of undeveloped land. The site is owned by Harris County Flood Control District and Westador MUD with MUD property granted to Harris County Flood Control District through Interlocal Agreement for the development of a flood reduction facility.
Expected Impact:
The purpose of this project is to help reduce the risk of flood damage within the Cypress Creek watershed.
Alternative Options:
A reduced capacity of the detention basin with smaller area without road abandonment.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service
Prior Court Action (if any): None
|
Date |
Agenda Item # |
Action Taken |
|
|
|
|
Location:
Address (if applicable): 0 Nanes Road, Houston TX 77090
Precinct(s): Precinct 1
|
Fiscal and Personnel Summary |
|
Service Name |
|
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$ |
$ |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$ |
$ |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: November 12, 2024
Anticipated Implementation Date (if different from Court date):
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Michael Ware, Director, Real Property Division
Attachments (if applicable): Abandonment Order with Exhibit; Location Map