Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN 201033962814
Vendor/Entity Legal Name (if applicable): GC Engineering, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with GC Engineering, Inc. in the amount of $45,547.00 for Professional Engineering Services in connection with Telge Road Segment 3 - Wyman Gordon Driveway to EB Frontage Road of US 290 - 2019, UPIN 201033962814, Precinct 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
The County executed an agreement for Professional Engineering Services with GC Engineering, Inc. in 2020 and now seeks to amend the agreement for the first time. This amendment will facilitate the additional design services to address TxDOT comments and complete the project design. The amendment entails additional traffic engineering services as required by TxDOT. Additionally, the amendment includes optional additional traffic engineering services to accommodate the proposed traffic signal at Northwest Lake Drive intersection.
Expected Impact:
This action will allow the firm to incorporate the necessary design changes to the eastbound US 290 Frontage at Telge Road and Northwest Lake Drive at Telge Road intersections.
Alternative Options:
The alternative is to not revise the plans, but then the plans will not be compatible with the needs of the project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
|
Date |
Agenda Item # |
Action Taken |
|
08/25/2020 |
1.g.6 |
Professional Engineering Services agreement approved on court agenda |
Location: Telge Road, Houston, TX 77095
Address (if applicable): N/A
Precinct(s): Precinct 3
|
Fiscal and Personnel Summary |
|
Service Name |
Engineering |
|
|
|
Current Fiscal Year Cost |
Annual Fiscal Cost |
|
|
Labor |
Non-Labor |
Total |
Recurring Expenses |
|
Funding Sources |
|
|
Existing Budget |
|
|
|
|
|
1070 - Mobility Fund |
$ |
$45,547.00 |
$45,547.00 |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Current Budget |
$ |
$45,547.00 |
$45,547.00 |
$ |
|
Additional Budget Request (Requires Fiscal Review Request Form) |
|
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Choose an item. |
$ |
$ |
$ |
$ |
|
Total Additional Budget Request |
$ |
$ |
$ |
$ |
|
Total Funding Request |
$ |
$45,547.00 |
$45,547.00 |
$ |
|
Personnel (Fill out section only if requesting new PCNs) |
|
|
Current Position Count for Service |
- |
- |
- |
- |
|
Additional Positions Request |
- |
- |
- |
- |
|
Total Personnel |
- |
- |
- |
- |
Anticipated Court Date: October 8, 2024
Anticipated Implementation Date (if different from Court date): N/A
Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item
Contact(s) name, title, department: Erwin Burden, P.E., CFM, Senior Director, Capital Project Infrastructure, Office of the County Engineer
Attachments (if applicable): Contract Amendment Documents