Legislation Details

File #: 26-4158    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 6/23/2026 In control: Commissioners Court
On agenda: 7/9/2026 Final action: 7/9/2026
Title: Request for approval of a change in contract with J Rivas Construction, LLC, in connection with Sidewalk and Trail Program - Precinct 4 - 2025, with no change in the contract amount, Job No. 25/0242-1, UPIN 25104MF3VR01, Precinct 4, MWBE Contracted Goal: 31.22%, MWBE Current Participation: 81.97%.

Primary Department: County Engineer

Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

 

Secondary Department: N/A

Secondary Department Head/Elected Official: N/A

 

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

 

Project ID (if applicable): Job No. 25/0242, UPIN 25104MF3VR01

Vendor/Entity Legal Name (if applicable): J Rivas Construction, LLC

 

MWBE Contracted Goal (if applicable): 31.22%

MWBE Current Participation (if applicable): 81.97%

Justification for 0% MWBE Participation Goal:  N/A - Goal is not 0% and is listed above

 

Grant Indirect Costs Rate (if applicable): N/A

Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

 

Request Summary (Agenda Caption):

title

Request for approval of a change in contract with J Rivas Construction, LLC, in connection with Sidewalk and Trail Program - Precinct 4 - 2025, with no change in the contract amount, Job No. 25/0242-1, UPIN 25104MF3VR01, Precinct 4, MWBE Contracted Goal: 31.22%, MWBE Current Participation: 81.97%.

end

 

Background and Discussion:

Project includes installation and repair of sidewalk and trail in Various Locations in Harris County Precinct 4.  The Precinct has requested for new bid items be added to the contract.  All missing in the current bid.  The new bid item is only to establish the unit price and there is no change to the contract amount.

 

Change includes adding bid Item #173 through 185:

1-                     Item 173 - Remove and Replace Small Traffic Box (all type)- $2500/EA

2-                     Item 174 - Remove and Replace Large Traffic Box (all type) - $4,850/EA

3-                     Item 175 - Adjust Large Traffic Sign box (all type) - $2,750/EA

4-                     Item 176 - Adjust Small Traffic Sign box (all type) - $1,800/EA

5-                     Item 177 - Project Sign - $1,300/EA.

6-                     Item 178 - PROJECT SITE DOCUMENTATION - $500.00/LS

7-                     Item 179 - SWPPP MONITORING AND DOCUMENTATION - $2,000/Month.

8-                     Item 180 - Removing Structures (Including Retaining Wall) - $500/EA

9-                     Item 181 - Clearance Prune Tree - $150/EA

10-                     Item 182 - Checker Plate Sidewalk (3/8" Thickness) - $60/SF

11-                     Item 183 - Retro reflectorized Pavement Markings (Type II) (12 in, Yellow, Solid) (6 in Curb Per Detail D) - $10/LF

12-                     Item 184 - Retro reflectorized Pavement markings (Type I) (24 in, Green, Solid, Thermoplastic) (90 mil) - $8/LF

13-                     Item 185 - PLACE, MAINTAIN AND REMOVE PROJECT SIGN (HARRIS COUNTY) - $1,000/EA

 

Expected Impact:

Change allows the contractor to comply with environmental requirements and respond to emergency calls within 6 hours.

 

Alternative Options:

Maintain the original scope of the project.

 

County Strategic Plan Goal:  2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.

County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.

Justice/Safety Initiative (Goal 1):  N/A

Infrastructure Initiative (Goal 2):  H1: Complete and implement the Flood Resilience Plan.

Economy Initiative (Goal 3): N/A

Health Initiative (Goal 4): N/A

Climate/Resilience Initiative (Goal 5): N/A

Housing Initiative (Goal 6): N/A

 

Additional notes related to the Strategic Plan: N/A

 

Prior Court Action (if any):

Date

Agenda Item #

Action Taken

09/18/2025

265 (25-5898)

Contract Award

05/14/2026

310 (26-3118)

Contract Renewal

 

Location:

Address (if applicable):

Precinct(s): Precinct 2

 

Fiscal and Personnel Summary

Service Name

Engineering

 

 

Current Fiscal Year Cost

Annual Fiscal Cost

 

Labor

Non-Labor

Total

Recurring Expenses

Funding Sources

 

Existing Budget

 

 

 

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Existing Budget

$

$

$

$

Additional Budget Request (Requires Fiscal Review Request Form)

 

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Choose an item.

$

$

$

$

Total Additional Budget Request

$

$

$

$

Total Funding Sources

$

$

$

$

Grants - Proposed Budget (For Grants Items only)

 

Labor

Non-Labor

Total

No. of Grant Years

Local Match Source - Existing Budget: Choose an item.

$

$

$

 

Local Match Source - Additional Budget Request: Choose an item.

$

$

$

 

Grant Funds Applied for/Awarded (Total)

$

$

$

 

Personnel (Fill out section only if requesting new Position Control Numbers (PCN)s)

 

Current Position Count for Service

-

-

-

-

Additional Positions Request

-

-

-

-

Total Personnel

-

-

-

-

 

County Attorney’s Office Legal Review (for Harris County Code Items only)

CAO Reviewer Name and Title

 

CAO Review Completion Date

Click or tap to enter a date.

 

Anticipated Court Date: 7/9/2026

Anticipated Implementation Date (if different from Court date): N/A

 

Emergency/Disaster Recovery Note: Not an emergency, disaster, or COVID-19 related item

 

Contact(s) name, title, department: Erwin Burden, PE, CFM, Chief of Engineering and Architectural Services, Harris County Office of the County Engineer

 

Attachments (if applicable): County Auditor’s Form 1258B